| Cost breakdown of the Paddington Health Campus | |||
| Capital costs summary | Costs exc VAT (£000s) | VAT (£000s) | Costs inc VAT (£000s) |
| Departmental costs | 187,412 | 32,797 | 220,209 |
| On costs | 339,209 | 59,362 | 398,571 |
| Works cost total | 526,621 | 92,159 | 618,780 |
| Provisional location adjustment | 121,123 | 21,197 | 142,320 |
| Fees | 58,297 | 58,297 | |
| Non-works costs | 17,646 | 3,088 | 20,734 |
| Planning contingency | 65,132 | 11,398 | 76,530 |
| Total (for approval purposes) | 788,819 | 127,842 | 916,661 |
| Inflation adjustments | 164,098 | 28,717 | 192,815 |
| Forecast for total out-turn cost | 952,917 | 156,559 | 1,109,476 |