| Balancing act: Breakdwon of costs | ||||
| GIA | Cost | Total | Cost | |
| m2 | m2 | (£) | % | |
| Demolition & alterations | 3,155 | 35.82 | 113,010 | 1.5 |
| Substructure | 3,155 | 134.92 | 425,660 | 5.6 |
| Frame & upper floors | 3,155 | 189.71 | 598,550 | 7.8 |
| Roof | 3,155 | 91.01 | 287,150 | 3.7 |
| Stairs | 3,155 | 106.56 | 336,210 | 4.4 |
| External walls, windows & doors | 3,155 | 219.34 | 692,010 | 9.0 |
| Internal walls & partitions | 3,155 | 43.85 | 138,350 | 1.8 |
| Internal doors | 3,155 | 82.19 | 259,320 | 3.4 |
| Wall finishes | 3,155 | 43.08 | 135,920 | 1.8 |
| Floor finishes | 3,155 | 52.87 | 166,790 | 2.2 |
| Ceiling finishes | 3,155 | 30.52 | 96,300 | 1.3 |
| Fixtures & fittings | 3,155 | 100.00 | 315,500 | 4.1 |
| Mechanical & electrical installations | 3,155 | 597.94 | 1,886,490 | 24.6 |
| Theatre equipment | 3,155 | 285.22 | 899,880 | 11.7 |
| Lift installation | 3,155 | 20.54 | 64,800 | 0.8 |
| External works | 3,155 | 43.95 | 138,670 | 1.8 |
| External services | 3,156 | 42.14 | 133,000 | 1.7 |
| Preliminaries, overhead and profit | 3,155 | 310.11 | 978,390 | 12.8 |
| Total construction cost | 2,430 | 7,666,000 | 100.0 | |
| * includes builders work | ||||