Table 1: House starts for Q3-Q4 of 1995 and 1996 | |||
Region | Q3-Q4 | Q3-Q4 | % |
1996 | 1995 | change | |
Greater London | 6,140 | 5800 | 6 |
South-east | 15,560 | 12,930 | 20 |
South-west | 7,160 | 5,340 | 34 |
East Midlands | 6,510 | 4,570 | 42 |
West Midlands | 6,410 | 5,300 | 21 |
East Anglia | 3,370 | 2,650 | 27 |
Yorkshire and Humberside | 5,670 | 5,010 | 13 |
North-west | 7,810 | 7,700 | 1 |
North | 3,260 | 2,600 | 25 |
Scotland | 8,170 | 6,990 | 17 |
Wales | 3,250 | 3,250 | 0 |
Northern Ireland | 4,060 | 3,590 | 13 |
UK | 77,370 | 65,730 | 18 |
Source: National House Building Council | |||
The table illustrates the sharp increases that have occurred in housebuilding activity, measured in new sarts on site, in all regions except Wales and the North-west. The South-east (including Greater London) accounted for 29% of all new house starts. |
Table 2: Average dwelling prices and inflation 1995-1996 | |||
Average new dwelling prices | Existing house prices | ||
Q4 1996 (£) | % change from | % change from | |
Q4 1995 | Q4 1995 | ||
Greater London | 129,011 | -2.1 | 15.6 |
South-east | 115,598 | 3.4 | 8.5 |
South-west | 84,684 | -0.2 | 7.4 |
East Midlands | 76,208 | 3.5 | 3.8 |
West Midlands | 88,452 | 7.8 | 6.8 |
East Anglia | 77,539 | -2.1 | 5.1 |
Yorkshire and Humberside | 77,573 | 0.4 | 5.3 |
North-west | 80,408 | 2.3 | 5.7 |
North | 73,255 | -6.7 | 4.8 |
Scotland | 75,820 | -1.7 | 5.1 |
Wales | 74,060 | 3 | 10.8 |
Northern Ireland | 69,782 | 14.9 | 14.3 |
UK average | 87,088 | 0.6 | 7.9 |
Source: Halifax Building Society | |||
The table shows that the rise in headline house price inflation has been largely confined to the existing house market. |
Table 3: Typical unit sizes and internal circulation for private urban housing | ||
House type | Gross internal area (m2) | Circulation allowance (%) |
One-bed apartment | 48-58 | 10-Dec |
Two-bed apartment | 75-85 | Nov-14 |
Three-bed apartment | 105-120 | 08-Oct |
One-bed loft | 58-65 | n/a |
Two-bed loft | 80-90 | n/a |
Three-bed loft | 110-125 | n/a |
Three-bed townhouse | 115-130 | 14-16 |
Four-bed townhouse | 155-165 | 16-18 |
Table 4: Median time to construct traditionally built houses | |
House type | Months |
Detached houses | 7 |
Detached bungalows | 8 |
Semi-detached houses | 7.5 |
Terraced houses | 8.5 |
Attached bungalows | 8 |
Flats and maisonettes | 10.5 |
Source: National House Building Council (based on data for homes started in 1995) |
BRESCU'S good practice guide | ||
Element | Standard practice | Good practice |
Roof | 150mm insulation | 200mm insulation |
Ground floor | Uninsulated | 50mm polystyrene underfloor batts |
Boiler | Conventional gas fan-assisted | Condensing gas fan-assisted |
Heating control | Ground-floor thermostat, no zoning | Zone control by multiple thermostats |
Primary pipework insulation | None | Insulated |
Cost breakdown | |||
Element cost (£) | Cost/m2 gfa (£) | % of total cost | |
Substructure | 32,200 | 27.4 | 3.98 |
Site clearance | Item @ | £1,500 | |
Foundations and ground slab: insitu concrete ground beams, masonry walls below damp-proof course, damp-proof coure, contractor-designed precast concrete floor units | 410 m2 @ | £70 | |
Extra over for lift pit construction | Item @ | £2,000 | |
Upper floors | 18,200 | 15.49 | 2.25 |
Contractor-designed precast concrete floor units | 824 m2 @ | £20 | |
Balconies: contractor-designed precast concrete units | 35 m2 @ | £50 | |
Extra over for circular columns | 1030 m @ | £30 | |
Allowance for structural steel truss to suspended section of main concourse floor | Item @ | £100 000 | |
Roof | 32,700 | 27.83 | 4.05 |
Softwood trussed rafters: 150 mm insulation quilt | 395 m2 @ | £18 | |
Clay pantiles: softwood battens, reinforced felt underlay | 435 m2 @ | £25 | |
Extra for hips, ridges, and so on, to hipped roofs | 175 m @ | £25 | |
Perimeter treatment to eaves, soffits and verges | 120 m @ | £15 | |
Roof finishes to balconies: concrete pavers, mastic asphalt, warm deck roof insulation, vapour barrier, insulation to soffit of slab | 55 m2 @ | £60 | |
Handrails to terraces and balconies | 45 m @ | £100 | |
Rainwater goods: PVCu gutters and accessories | 125 m @ | £6 | |
Stairs | 13,800 | 11.74 | 1.71 |
Precast concrete stairs and half-landing: rise 2.70m | 3 @ | £4,000 | |
Softwood spiral staircase: overall rise 2.70m | 1 @ | £1,000 | |
Access stair to roof void | Item @ | £800 | |
External walls | 72,000 | 61.28 | 8.91 |
Cavity walls: two skins blockwork, insulated cavity, render, masonry paint finish to walling at ground level only | 155 m2 @ | £80 | |
Cavity walls: London stock facing bricks, 150mm medium-density blockwork inner skin, insulated cavity | 485 m2 @ | £75 | |
Reconstituted stone string-courses, copings and sills | 330 m @ | £40 | |
Allowance for additional architectural detailing | Item @ | £10,000 | |
Windows and external doors | 71,600 | 60.94 | 8.86 |
PVCu windows and screens: double-glazed sealed units, lintels, cavity trays, ironmongery, window boards, and so on | 215 m2 @ | £230 | |
Extra for doors in glazed screens to balconies | 28 @ | £500 | |
Glazed entrance screen and door: hardwood frame | 15 m2 @ | £500 | |
Window safety rails: powder-coated mild steel | 6 m @ | £100 | |
Internal walls and partitions | 39,400 | 33.53 | 4.88 |
Party walls: 215mm solid dense concrete blockwork | 550 m2 @ | £30 | |
Blockwork partitions: average 140mm thick | 170 m2 @ | £18 | |
Timber stud partitions: 100 mm thick, quilt insulation | 260 m2 @ | £30 | |
Glazed screen to stair lobbies: single-leaf panelled door | 4 @ | £3,000 | |
Internal doors | 32,100 | 27.32 | 3.97 |
Entrance doors: single-leaf, frame, ironmongery | 12 @ | £520 | |
Fire-rated doors: single-leaf, frame, ironmongery | 41 @ | £325 | |
Unrated doors: single-leaf, frame, ironmongery | 50 @ | £250 | |
Wall finishes | 25,600 | 21.79 | 3.17 |
Plasterboard drylining to blockwork | 860 m2 @ | £6 | |
Ceramic tiling to kitchens and bathrooms | 190 m2 @ | £50 | |
Decorations: two coats emulsion paint | 2950 m2 @ | £2 | |
Allowance for picture rails and trims | Item @ | £5,000 | |
Floor finishes | 28,400 | 24.17 | 3.51 |
Proprietary floating floor system: 22 mm chipboard, foam-backed softwood battens | 920 m2 @ | £16 | |
Sand/cement screed: mesh reinforcement, resilient closed-cell foam layer | 105 m2 @ | £10 | |
Ceramic floor tiles to kichens | 100 m2 @ | £50 | |
Carpet to communal lobbies | 60 m2 @ | £35 | |
Moulded softwood skirtings | 970 m @ | £4 | |
Cove ceramic skirting to kitchens | 110 m @ | £15 | |
Ceiling finishes | 11,100 | 9.45 | 1.37 |
Two layers plasterboard: two coats emulsion paint | 820 m2 @ | £10 | |
Coving to reception rooms and bedrooms | 970 m @ | £3 | |
Furniture and fittings | 180,900 | 153.96 | 22.39 |
Allowance for fully-fitted kitchen to developer's specification: units, oven, hob, extractor hood, mircrowave, fridge, freezer, dishwasher, washer-drier and waste disposal | 12 @ | £12,000 | |
Allowance for built-in bedroom furniture | 12 @ | £3,000 | |
Bathroom mirrors | 24 @ | £25 | |
Matwell to communal lobby | Item @ | £300 | |
Sanitary fittings | 42,000 | 35.74 | 5.2 |
Allowance for sanitary fittings: fully-fitted bathroom/shower room to developer's specification, two WCs, two wash-hand basins, bath, shower, including all fixtures and fittings | 12 @ | £3,500 | |
Disposal installations | 5,100 | 4.34 | 0.63 |
PVCu rainwater downpipes and fittings | Item @ | £1,000 | |
PVCu soil and vent pipework and fittings | 1175 m2 @ | £13.50 | |
Water installations | 15,900 | 13.53 | 1.97 |
Hot and cold water supply: dedicated mains service to each dwelling, direct mains feed to all cold water outlets, calorifier, pipework and fittings | 1175 m2 @ | £13.50 | |
Space heating and ventilation | 45,900 | 39.06 | 5.68 |
Low-pressure hot-water central heating sytem: fan-assisted blanced-flue boiler, wall-mounted steel-panel radiators, single-zone thermostatic control | 1175 m2 @ | £35 | |
Extract fans and ductwork to kitchens and bathrooms | 19 @ | £250 | |
Electrical installations | 29,400 | 25.02 | 3.64 |
Mains and sub-mains installation | Item @ | £5,000 | |
Small power installation to apartments | 1115 m2 @ | £9 | |
Lighting and luminaires to apartments | 1115 m2 @ | £12 | |
Emergency lighting, lighting and small power to common areas | Item @ | £1,000 | |
Lift installation | 20,000 | 17.02 | 2.48 |
Eight-person, 0.4 m/second, electro-hydraulic lift | Item @ | £20,000 | |
Communicative installations | 17,800 | 15.15 | 2.2 |
Telephone points | 24 @ | £50 | |
Socket points for cable-access television | 24 @ | £250 | |
Mains-operated smoke alarms | 24 @ | £150 | |
Closed-circuit television entry-phone system | Item @ | £7,000 | |
Preliminaries and contingencies | 66,900 | 56.94 | 8.28 |
Management costs, site establishment and supervision, allow 7% | £51,900 | ||
Contingency sum, allow 2% | £15 000 | ||
Total construction cost : building only | 808 000 | 687.66 | 100 |
Element cost (£) | Cost/m2 gfa (£) | % of total cost | |
Site works | 33,200 | 28.25 | n/a |
Surface car parking and access roads, coated macadam on granular fill, including allowance for external lighting | 600 m2 @ | £27 | |
Paths and walkways: brick and block pavers on sand base, kerbs and edgings | 200 m2 @ | £35 | |
Soft landscaping: imported top soil, cultivate, turf, plants and mature trees | Item @ | £7,000 | |
Ornamental railings and street furniture | Item @ | £3,000 | |
Drainage | 15,000 | 12.77 | n/a |
Clayware and PVCu below-ground drainage | Item @ | £5,000 | |
Allowance for manholes and inspection chambers | Item @ | £10,000 | |
External services | 30,000 | 25.53 | n/a |
Share of costs of extending mains services from site boundary and connection charges | Item @ | £30,000 | |
Minor building works | 3,500 | 2.98 | n/a |
Masonry-built bin stores to match main building | Item @ | £3,500 | |
Preliminaries and contingencies | 7,300 | 6.21 | n/a |
Management costs, site establishment supervision, allow 7% | ghjlhjlk | £5,700 | |
Contingency sum, allow 2% | gl;hk;hkl | £1,600 | |
Total construction cost : external works only | 89,000 | 75.74 | n/a |
Overall construction cost | 897,000 | 763.4 | n/a |
net extra (saving) cost/m2 gfa (£) | |||
Alternative element specifications | |||
(extra over costs are inclusive of preliminaries and contingencies) | |||
Substructure | |||
Contaminated land: share of site investigation costs - item @ £1500 | 1.39 | ||
Site clearance: disposal of contaminated waste (assumed 50% normal, 50% polluting). Rate excludes landfill tax - 1000 m3 @ £15 | 13.91 | ||
Methane gas membrane, laid on hardcore bed and blinding with insitu concrete ground slab - 410 m2 @ £30 | 3.42 | ||
Extra over for insulation to ground floor slab - 410 m2 @ £6 | 2.28 | ||
Extra over for piled foundations - 410 m2 @ £95 | 36.64 | ||
Semi-basement car park of insitu concrete frame and retaining walls complete with drainage and surfacing - 410 m2 @ £205 | 68.04 | ||
External walls | |||
Cavity wall: two-skin blockwork, insulated cavity, Western red cedar weather boarding - 160 m2 @ £78 | 0.45 | ||
Windows and external doors | |||
Softwood windows and screens instead of PVCu - 215 m2 @ £280 | 9.97 | ||
Hardwood windows and screens instead of PVCu - 215 m2 @ £340 | 21.94 | ||
Internal walls and partitions | |||
Metal stud partitions instead of timber - 260 m2 @ £35 | 1.21 | ||
Floor finishes | |||
Quarry tiles to kitchen instead of ceramic - 100 m2 @ £27 | -2.13 | ||
Space heating and ventilation | |||
Extra over for condensing fan-assisted gas boiler - 12 @ £300 | 3.51 | ||
Extra over from room thermostats - item @ £2000 | 1.95 | ||
Communications installations | |||
Voice-only entryphone sytsem - item @ £2500 | -4.38 |
Regional variations | |
All costs in this model are based on a scheme in outer London and should be adjusted by the following location factors for schemes in other areas: | |
Inner London | 1.06 |
South-east | 0.97 |
South-west | 0.92 |
East Anglia | 0.91 |
East Midlands | 0.88 |
West Midlands | 0.89 |
Yorkshire and Humberside | 0.9 |
North-west | 0.93 |
North | 0.91 |
Scotland | 0.92 |
Wales | 0.88 |
Northern Ireland | 0.77 |