| Design issues for specialist space | |
| Libraries and learning resource centres | |
| Design drivers | Solutions |
| Continuing expansion of library collections | Greater use of electronic journals, provision of flexible internal accommodation to allow for growth of hard and soft copy collections |
| Increasing requirements for group-based working | Provide separate spaces for quiet and group working and special consideration of acoustic management in open-plan areas |
| Greater use of IT | Provide central IT resource areas to reduce network costs and to control noise. Increase space allowances to permit screen and desk working. Provide quiet work space for book-based study |
| Environmental control | Maximise natural ventilation and daylight where possible. Restrict use of cooling to archive and IT areas only where conditions require it |
| Research facilities | |
| Need to attract research scientists and external funding | High-quality architecture, high standards of internal and external environment and up-to-date equipment |
| Facilitation of creative multidisciplinary working | Provision of hierarchy of workplaces to enable group and solo working and range of spaces to encourage interaction |
| Flexibility to accommodate change | Flexible fit-out and servicing solutions that facilitate replanning and restacking |
| Separation of undergraduate teaching and graduate research activities | Clear separation of activities either through the development of stand-alone buildings or the internal planning of larger schemes |
| Laboratories | |
| Close environmental control | Extensive, high-capacity building services, large ceiling voids, solid floor slabs to control vibration and avoid infestation in floor voids |
| Quality of working environment | Quality of write-up areas, flexibility of lab space and quality of natural light and air-conditioning systems |
| Flexibility | Modular laboratory design and services distribution, easily accessible services installations, independent structure and services |
| Security to protect research projects and equipment | Physical and electronic security measures, balanced against requirements to promote interaction between researchers. Specialist security for animal houses and other high-risk areas |
| Teaching spaces | |
| Flexible floorplates | Column-free space, lightweight partitions, regular planning grid, small power and IT distribution equivalent to commercial office standards to provide flexibility for replanning |
| High-quality space | Shallow floor plates of 12-15 m for daylight and natural ventilation, clear orientation, use of atriums to provide circulation and social space, use of good-quality, robust materials |
| Low operational costs | Natural ventilation, limited cooling and ventilation for peak lopping only, and use of cost-effective sustainability features |
| Cost breakdown | ||
| Element cost | cost/m2 gfa £ | |
| Substructure | 979,000 | 222.5 |
| Basement construction; excavation and disposal; reinforced insitu concrete ground beams, walls and suspended slab; vapour barrier and protection board; average depth 4.60 m 1300 m2 @ 400 | ||
| Piling; 600 diameter; average 35 m long; testing; disposal 48 @ 2500 | ||
| Contiguous piling; 450 and 600 diameter; average 17 m long; testing; disposal 190 @ 1400 | ||
| Allowance for additional foundation works Item @ 3000 | ||
| Allowance for incoming services Item @ 70,000 | ||
| Frame and upper floors | 718,000 | 163.18 |
| Insitu reinforced concrete columns, core walls and suspended slabs; 400 thick 4000 m2 @ 170 | ||
| Extra for exposed trough slab; 400 thick 1450 m2 @ 8 | ||
| Structural steel frame; hollow sections at roof level; surface finishes; erection 24t @ 1100 | ||
| Roof | 307,100 | 69.8 |
| Zinc raised seam roofing; 0.8 mm thick; low pitch; softwood roof members, plywood deck; vapour barrier, insulation 425 m2 @ 130 | ||
| Inverted mastic asphalt roof; lightweight screed, average 105 thick; isolating layer; rigid board insulation; gravel ballast, 80 mm thick; including detailing to kerbs for plant and rooflights 495m2 @ 120 | ||
| Proprietary opening rooflights; double glazed; Velux; average size 1 m2 32 @ 1000 | ||
| Purpose made patent glazing; aluminium glazing bars; sealed double glazed units 280 m2 @ 350 | ||
| Allowance for flashings; fascias; sheathing felt etc Item @ 20,000 | ||
| Rainwater goods; gutters and roof outlets Item 14,000 | ||
| Cleaning gantry Item @ 18,000 | ||
| Mansafe system Item @ 5,200 | ||
| Pavement rooflights; smoke vents 12 m2 @ 440 | ||
| Stairs | 97,000 | 22.05 |
| Insitu reinforced concrete stairs and half landings; 1600 wide; 3.7 m average rise 8 @ 4800 | ||
| Allowance for balustrades and handrails 190 m @ 140 | ||
| Allowance for roof level access ladders 4 @ 3,000 | ||
| Allowance for catwalks and platforms in plant rooms Item @ 20,000 | ||
| External walls | 208,500 | 47.39 |
| Cavity wall construction; facing bricks; blockwork; DPCs; insulation; lintels 345 m2 @ 100 | ||
| Cavity wall construction; facing bricks; built against concrete walls; DPCs; insulation; lintels 690 m2 @ 80 | ||
| Precast concrete copings 250 m @ 75 | ||
| Windows and external doors | 301,200 | 68.45 |
| Proprietary steel-framed, double-glazed windows; polyester powder-coated 75 m2 @ 380 | ||
| Curtain walling; steel frame; sealed double-glazed units ; insulated steel-faced spandel panels; polyester powder-coated 470m2 @ 450 | ||
| Clerestory windows; sealed double-glazed louvre motorised units; controls 30 m2 @ 900 | ||
| External doors; double-glazed, steel-framed doors and doorsets; polyester powder-coated; stainless steel ironmongery 10 @ 1700 | ||
| External doors; aluminium louvre doors and doorsets; polyester powder-coated; stainless steel ironmongery 7 @ 800 | ||
| Allowance for security shutters Item @ 2000 | ||
| Window boards; painted 320 m 30 | ||
| Internal walls and partitions | 160,000 | 36.36 |
| Partitions; facing blockwork; 150 average thickness (average rate); ancillaries 1340 m2 @ 40 | ||
| Extra over for 215 thick blockwork 450 m2 @ 15 | ||
| Stud partition; ancillaries; acoustic sealants 1600 m2 @ 50 | ||
| Allowance for fire-rated drylining to service risers 360 m2 @ 40 | ||
| Cubicle partitions; polyester powder-coated, steel-faced composite panels 12 @ 440 | ||
| Internal doors | 177,900 | 40.43 |
| Flush doors; solid core; ply-faced; vision panels; wrot softwood frame; 30/30 fire resistance; stainless steel door furniture; decorations 200 @ 800 | ||
| Extra for; oak veneer finish 70 @ 170 | ||
| Allowance for borrowed lights Item @ 6000 | ||
| Wall finishes | 71,600 | 16.27 |
| Plasterboard wall linings; timber battens; ancillaries 2070 m2 @ 14 | ||
| Two-coat plasterwork 1060 m2 @ 10 | ||
| Skim coat; to plasterboard 760 m2 @ 4 | ||
| Ceramic tiles 100 m2 @ 50 | ||
| Painting plaster two coats emulsion paint 8000 m2 @ 3 | ||
| Floor finishes | 348,000 | 79.09 |
| Hardwood flooring; clear lacquer finish 100 m2 @ 80 | ||
| Raised access floor; 150 average cavity depth; dust sealer to cavity 2600 m2 @ 50 | ||
| Extra for acoustic and fire cavity barriers 2600 m2 @ 5 | ||
| Allowance for floor diffusers 260 @ 100 | ||
| Allowance for services bridges Item @ 5000 | ||
| Screeds; sand cement and proprietary concrete screeds; average 60 thick; | ||
| average rate used 825 m2 @ 20 | ||
| Extra for insulation board 140 m2 @ 18 | ||
| Carpet tile; to general areas 2900 m2 @ 30 | ||
| Rubber tile safety flooring; skirting 210 m2 @ 56 | ||
| Rubber sheet flooring; to general areas 680 m2 @ 37 | ||
| Floor paint; to plant rooms 390 m2 @ 4 | ||
| Softwood skirting; painted 1950 m @ 10 | ||
| Ceiling finishes | 63,900 | 14.52 |
| Allowance for mats and matwells Item @ 2000 | ||
| Suspended ceilings; plasterboard on MF; access panels; paint finish 750 m2 @ 30 | ||
| Allowance for radiant panel ceiling Item @ 22,000 | ||
| Plasterboard linings; access panels; paint finish 560 m2 @ 20 | ||
| Painting; to exposed concrete ribbed soffits; one coat clear sealer 4100 m2 @ 2 | ||
| Furniture | 307,000 | 69.77 |
| Purpose-made fixed furniture; tables and seating to non-teaching areas Item @ 150,000 | ||
| Reception desk Item @ 20,000 | ||
| Lecture theatre and seminar room equipment; whiteboards, hanging rails, | ||
| flipcharts and pinboards Item @ 60,000 | ||
| Fixed seating to lecture theatre 200 @ 150 | ||
| Window blinds 300 m2 @ 50 | ||
| Motorised blind to skylight Item @ 5000 | ||
| Blackout blinds to teaching spaces Item @ 25,000 | ||
| Statutory and orientation signage Item @ 2000 | ||
| Sanitary fittings | 54,400 | 12.36 |
| WCs, urinals, washhand basins, fittings; cleaners’ sinks; complete (average rate) 80 @ 260 | ||
| Extra for fittings for disabled WCs 5 @ 400 | ||
| IPS system panels; including access panels; ancillaries 80 m2 @ 200 | ||
| Modular washroom units; stainless steel 8 @ 1600 | ||
| Hand dryers 14 @ 200 | ||
| Disposal installations | 103,600 | 23.55 |
| Rainwater downpipes, outlets and connections to drains 4400 m2 @ 10 | ||
| Extra for basement drainage 1300 m2 @ 12 | ||
| Waste, soil and vent installation; PVCu pipework and fittings 4400 m2 @ 10 | ||
| Water installations | 83,400 | 18.95 |
| Mains water; cold water storage and distribution, water treatment 4400 m2 @ 10 | ||
| Hot water installation; calorifiers; distribution; insulation 4400 m2 @ 6 | ||
| Local water heaters; distribution; insulation Item @ 13,000 | ||
| Space heating and air treatment | 583,600 | 132.64 |
| Boiler; 575 kW, pumpset and pipework in plantroom; flue Item @ 62,000 | ||
| Chilled water plant; 260kW; pipework and valves in plantrooms and risers Item @ 49,000 | ||
| Air handling units; supply and extract; total mass flow rate 17 kg/s Item @ 82,000 | ||
| LTHW distribution pipework; ancillaries; insulation 4400 m2 @ 20 | ||
| Chilled water distribution pipework; ancillaries; insulation 1930 m2 @ 10 | ||
| Supply and extract ductwork; grilles and diffusers; ancillaries; including allowances for two-hour fire-rated smoke extract ductwork 1930 m2 @ 90 | ||
| LTHW heating; trench heating Item @ 26,000 | ||
| LTHW heating; panel radiators Item @ 34,000 | ||
| Allowance for radiant panel heating and cooling installation to double height spaces 485 m2 @ 40 | ||
| Allowance for supplementary cooling to ICT rooms; packaged DX units Item @ 17,000 | ||
| Toilet extract installation 4400 m2 @ 3 | ||
| Electrical installations | 444,500 | 101.02 |
| Mains and sub – mains installation 4400 m2 @ 20 | ||
| Small power installation 4400 m2 @ 20 | ||
| Extra over for small power to offices and IT areas; floor outlet boxes 1800 m2 @ 5 | ||
| Lighting and luminaires; generally 4400 m2 @ 35 | ||
| Extra for enhanced lighting; public spaces and cellular offices 1700 m2 @ 45 | ||
| Emergency lighting; generally 4400 m2 @ 5 | ||
| Power supply installation to mechanical equipment Item @ 7000 | ||
| Gas installation | 13,000 | 2.95 |
| Gas supply to central boiler and kitchen area Item @ 13,000 | ||
| Lift installation | 86,000 | 19.55 |
| Four-person electric traction lift serving five floors 2 @ 43000 | ||
| Protective installations | 22,200 | 5.05 |
| Lightning protection 4400 m2 @ 2 | ||
| Earthing and bonding 4400 m2 @ 1 | ||
| Dry riser 1 @ 9000 | ||
| Communications installation | 152,900 | 34.75 |
| Fire alarm installation; smoke detectors; call points 4400 m2 @ 15 | ||
| Disabled alarm Item @ 3000 | ||
| Structured cabling installation; 120% capacity 1250 m2 @ 25 | ||
| Security and access control system; intruder alarm 4400 m2 @ 4 | ||
| Allowance for CCTV system Item @ 20000 | ||
| Telephone and data wireways; for ICT, CCTV and security systems Item @ 15000 | ||
| Special installations | 110,000 | 25 |
| Building management system 4400 m2 @ 25 | ||
| Builder's work in connection | 82,700 | 18.8 |
| Forming holes, chases etc Allow 5% Item @ 82700 | ||
| Preliminaries and contingencies | 995,800 | 226.32 |
| Testing and commissioning of services; record drawings Item @ 10,000 | ||
| Management costs, site establishment and site supervision Allow 13% Item @ 711,800 | ||
| Contingency sum Allow 5% Item @ 274,000 | ||
| Total construction cost – building only | 6,471,300 | 1470.75 |
| Location factors | |
| Inner London | 1.06 |
| South-east | 0.97 |
| South-west | 0.91 |
| East Midlands | 0.90 |
| West Midlands | 0.89 |
| East Anglia | 0.91 |
| Yorkshire and Humberside | 0.85 |
| North-west | 0.90 |
| Northern | 0.86 |
| Scotland | 0.87 |
| Wales | 0.85 |
| Northern Ireland | 0.73 |
| Indicative costs of university buildings | |
| Building type | £/m2 gifa |
| Humanities teaching building | 1100 to 1600 |
| Science laboratory buildings | 1500 to 2400 |
| Libraries | 1300 to 2000 |
| Learning resource centres | 1300 to 1800 |
| Lecture theatres | 1300 to 1500 |
| Costs are current in fourth quarter 2002, based on a location in outer London. Costs are for the building only, and exclude demolitions, loose furniture and fittings, external works, professional fees and VAT. | |