- News

All the latest updates on building safety reformRegulations latest 
 - Focus
 

    All the latest updates on building safety reform



| Warwick University International Manufacturing Centre, phase three: elemental cost plan | ||||
| Gross internal floor area 4372 m2 | ||||
| Works package | estimated final cost £ | cost/m2 | % cost | Outline specification | 
| substructure and drainage | 245,000 | 56.04 | 5.63% | excavated deep-pad foundations | 
| demolition | 19,700 | 4.51 | 0.45% | |
| superstructure | 492,800 | 112.72 | 11.33% | steel frame with exposed Tarmac Spirol precast concrete plank upper floors and roof | 
| intumescent paint to steel frame | 22,000 | 5.03 | 0.51% | |
| screeding | 137,500 | 31.45 | 3.16% | structural screed toppings to floors and roof | 
| roof cladding | 88,600 | 20.27 | 2.04% | Rigidal Ziplok Aluminium Roofing system | 
| asphalt | 8900 | 2.04 | 0.2% | |
| stairs | 49,900 | 11.41 | 1.15% | steel prefabricated staircases with tile/vinyl finishes | 
| masonry | 310,700 | 71.07 | 7.14% | Baggeridge Blue engineering bricks externally, medium-density blockwork internally | 
| sealants and diamond drilling | 15,000 | 3.43 | 0.34% | |
| eternit cladding | 74,000 | 16.93 | 1.7% | Eternit Alucomat white cladding panel system | 
| Kalwall fenestration | 88,400 | 20.22 | 2.03% | Kalwall translucent insulated curtain walling system | 
| louvres | 25,700 | 5.88 | 0.59% | |
| windows and curtain walling | 305,000 | 69.76 | 7.01% | W40 steel windows and curtain walling | 
| joinery and internal finishes | 485,000 | 110.93 | 11.15% | plaster to blockwork; Gyproc metal-framed system suspended ceilings and Hunter Douglas C-Grid Access Ceiling | 
| bridge link and metalwork | 118,000 | 26.99 | 2.71% | |
| electrical Installation | 539,000 | 123.28 | 12.39% | |
| mechanical installation | 472,000 | 107.96 | 10.85% | heating, ventilation and cooling by four distributed air handling units; space heating by campus combined heat and power system | 
| lift installation | 35,000 | 8.01 | 0.8% | |
| external works | 70,000 | 16.01 | 1.61% | |
| minor building works | 15,000 | 3.43 | 0.34% | |
| roller shutter doors | 3500 | 0.80 | 0.08% | |
| scaffolding | 86,000 | 19.67 | 1.98% | |
| tower crane | 80,000 | 18.30 | 1.84% | |
| works contracts total | 3,786,700 | 866.13 | 87.03% | |
| Management contractor | ||||
| preliminaries and fees | 563,300 | 128.84 | 12.97% | |
| Estimated construction costs | 4,350,000 | 994.97 | ||
| Additions to original scope of work | ||||
| work to plant room, column casing and etched glass | 38,000 | |||
| Original contract cost plan total | 4,314,000 | 986.73 | ||