| Cost analysis of Coin Street site B | ||||
| Housing and retail £/m2 7056m2 gifa | Car park £/m2 7001m2 gifa | Total £/m2 | Outline specification | |
| Enabling works | 40.05 | 19.95 | ||
| Substructure | 128.56 | 64.03 | Suspended reinforced concrete slab foundations | |
| Superstructure | ||||
| Frame | 5.25 | 4.08 | 4.67 | Insitu reinforced concrete frame; Everdure Caltite waterproof concrete deck over car parking |
| Upper floors | 117.29 | 1.07 | 59.41 | Insitu reinforced concrete |
| Roof | 66.60 | 83.35 | 74.94 | Exposed Douglas fir joists with plydecking and standing-seam Rhinezinc; insitu RC paved terrace |
| Stairs | 37.47 | 0.96 | 19.29 | Prefab timber to dwellings; painted steel frames and screed infill |
| External walls | 102.16 | 10.32 | 56.42 | Chelwood Sunbury red handmade brick, cavity and dense blockwork; Vitex Cofassus hardwood cladding |
| Windows and external doors | 122.83 | 3.00 | 63.15 | Wicona polyester powder-coated aluminium system |
| Internal walls and partitions | 55.11 | 3.67 | 29.49 | Dense concrete blockwork plastered |
| Internal doors | 32.49 | 3.16 | 17.88 | Solid-core doors painted, plus fire-rated glass panels to kitchen |
| Finishes and fixtures | ||||
| Wall finishes | 41.10 | 0.52 | 20.89 | Paint finish on plaster; Fendor Hansen lift screens |
| Floor finishes | 42.09 | 0.55 | 21.40 | Danskin timber floating floor; Freudenberg vinyl |
| Ceiling finishes | 26.18 | 0.06 | 13.17 | Painted plasterboard |
| Fixtures and fittings | 21.89 | 0.55 | 11.26 | |
| Services installation | ||||
| Sanitary installation | 8.71 | 0.04 | 4.39 | |
| Disposal installation | 19.72 | 1.54 | 10.67 | |
| Water installation | 39.82 | 7.67 | 23.81 | Condensing boilers, solar panels |
| Heat source | 18.07 | 9.07 | ||
| Space heating/air treatment | 6.27 | 3.15 | ||
| Ventilating system | 44.85 | 38.16 | 41.52 | Heat-recovery ventilation system |
| Electrical installation | 37.47 | 20.34 | 28.94 | By Briggs Forrester; Erco lighting for common parts |
| Gas installation | 4.43 | 2.22 | ||
| Lift installation | 7.13 | 2.52 | 4.83 | European Lifts side-action traction passenger lift |
| Protective installation | 2.56 | 27.11 | 14.79 | Sprinklers to car park |
| Communications installation | 7.53 | 3.78 | ||
| Special installation | 7.51 | 3.77 | ||
| Builders’ work in connection | 15.36 | 3.17 | 9.29 | |
| External works and overheads | ||||
| External works | 104.76 | 17.41 | 61.26 | |
| Preliminaries | 134.88 | 48.52 | 91.87 | |
| Contingencies | 9.08 | 3.27 | 6.19 | |
| Total | £1,138.61 | £449.65 | £795.50 | |
| Costs are based on original tender of February 1999, covering main and enabling contracts but excluding professional and statutory fees. | ||||