| Cost outline for building one | |
| Package | cost (£) |
| Shell and core | |
| perimeter steelwork | 860 124 |
| concrete frame | 2 148 241 |
| brick/blockwork | 38 476 |
| curtain walling | 1 423 225 |
| external architectural metalwork | 224 848 |
| roofing | 196 497 |
| drylining | 378 951 |
| suspended ceilings | 20 045 |
| raised floors | 26 730 |
| atrium stone floor | 48 000 |
| floor finishes | 12 655 |
| sundry metalwork | 27 000 |
| decorations | 24 279 |
| toilet fit-out/joinery | 629 899 |
| reception desk | 16 761 |
| mechanical services | 271 561 |
| ductwork | 461 663 |
| O&M manuals | 12 834 |
| commissioning | 16 800 |
| BMS | 124 799 |
| electrical services | 428 212 |
| lift installations | 364 152 |
| Total shell and core | 7 764 752 |
| Category A fit-out | 1 547 066 |
| Total construction | 9 311 818 |