| A typical week’s look-ahead form filled out by trade contractors | |||||||||||
| How building contractor Simons performed in the week from 16 November 1998 | |||||||||||
| Activity | Make-ready needs | Target % | Mon | Tue | Wed | Thur | Fri | Sat | Sun | Complete % | Reason for delay |
| Public WCs | |||||||||||
| Install laminated panels | 100 | ← | → | 80 | late materials | ||||||
| Install toilet cubicles | laminated panels in place | 100 | ← | → | 100 | ||||||
| Install mirrors | 100 | ← | → | 0 | change in priorities | ||||||
| BAA signage | 100 | ← | → | 80 | supplier pre-requisite | ||||||
| Doors and ironmongery | prime/undercoat frames | 100 | ← | → | 50 | supplier pre-requisite | |||||
| Reclaim Hall | |||||||||||
| Install magnagrid ceiling | services | 60 | ← | → | 60 | insufficient labour | |||||
| Hang CIBA GEIGY panels | 60 | ← | → | 60 | |||||||
| B/Work to G.L 42 | 100 | ↔ | 0 | pm/cm pre-requisite | |||||||
| Remove hoarding 12 | airside/landside barrier in place | 50 | ↔ | 0 | pm/cm pre-requisite | ||||||
| Terracotta bulkhead | 100 | ← | → | 0 | materials not delivered | ||||||
| Workable backlog | |||||||||||
| Firestop G.L 42 | services complete | 100 | ← | → | 100 | ||||||
| Cost data | |
| Package | Cost (£) |
| Floor finishes | 11 137 |
| Customer service desks | 4 626 |
| Baggage handling | 616 000 |
| General building work | 1 001 000 |
| Services | 659 816 |
| Ductwork | 145 883 |
| Fire alarms | 50 068 |
| Total construction (with sundries and overheads) | 2 773 832 |
| Project fees | 864 057 |
| Planning, etc | 51 570 |
| Design development and construction efficiency | 20 937 |
| Risk and inflation | 117 585 |
| Total cost | 3 827 981 |