| Boots vs BA: offices of the future compared | |
| Boots head office, Nottinghamshire | British Airways head office, Heathrow |
| 41 000 m2 for 2500 staff (including refurbished block) designed by DEGW | 120 000 m2 for 3000 staff and 1850 cars, designed by Niels Torp |
| Catalyst for increasing productivity | Same |
| Open-plan interior; clusters of individual and shared settings | Same |
| Mobile IT equipment for all staff | Same |
| Internal “street” forms main spine | Same |
| Out-of-town complex in parkland | Same |
| Two rectangular deep-plan blocks with narrow entrance link | Six horseshoe-shaped blocks linked by a glazed street |
| Two- and three-storey buildings partly sunk into ground, with adjacent surface car parking | Four-storey buildings above two-storey basement car parks, in landscaped parkland |
| Predominantly natural daylighting through several atria | Natural daylighting in narrow buildings |
| Deep-plan environment for low energy consumption | Air-conditioned as windows fixed to block aircraft noise |
| Predicted energy consumption 215 kWh/m2 a year (new block) | Energy consumption figures unavailable |
| Small restaurant in spine street (main restaurant elsewhere) | Two cafés in spine street, four restaurants overlooking lake |
| Construction managed (by Mace) | Same |
| Construction cost including fit-out (new block only) £54m, or £1368/m2 | Construction cost including fit-out, car parking and parkland £163m, or £1378/m2 |
| Cost Summary | |
| External Work | £81/m2 |
| Substructure | 68/m2 |
| Shell-and-core superstructure | 400/m2 |
| Shell-and-core services | 134/m2 |
| Category A fit-out, including M&E | 358/m2 |
| Category fit-out, including furniture | 327/m2 |
| Total construction cost | 1368/m2 |