| Comparison of services design criteria: offices and call centres | |||
| Design criteria | Specification standard British Council for Offices (best practice in the specification for offices) | Call centre floor (typical specification) | |
| Occupational density indoor climate control (person/m2) | 1:14 | 1:5-1:8 | |
| WC provision (gender split/person/m2) | 60/60 @ 1:14 | 70/60 @ 1:8 | |
| Fresh air ventilation (litres/sec/person) | 8-12 | 12 | |
| Cooling loads | – small power (W/m2) | 15 | up to 60+ |
| – lighting (W/m2) | 12 | 15 | |
| Primary power | – equipment (W/m2) | 15-25 | up to 70+ |
| – lighting (W/m2) | 12 | 15 | |
| Lighting | – office areas (lux) | 350-400 | 350-400 |
| Cost breakdown | |||
| element cost £ | £/m2 gifa | % of total cost | |
| Substructure | 390 000 | 49.37 | 4.42 |
| Ground slab; 200 mm thick reinforced insitu concrete bed, hardcore; damp-proof membrane; reinforced concrete column bases | 6500 | m2 @ | £55 |
| Allowance for below-ground drainage and incoming services | 6500 | m2 @ | £5 |
| Frame | 517 100 | 65.46 | 5.87 |
| Structural steel framing; 30 m clear span; allowance based on 50 kg/m2 (average rate for universal and hollow sections) | 325 | t @ | £1,200 |
| Allowance for structural steelwork to mezzanine based on 35 kg/m2 | 50 | t @ | £1,050 |
| Cold-rolled galvanised steel roof purlins; 1.6 m centres; 4.5 kg/m2 average weight | 5500 | m @ | £6 |
| Fire protection ; rigid board fire protection; one-hour fire resistance to columns | 700 | m2 @ | £20 |
| Fire protection; intumescent paint; one-hour fire resistance to exposed roof structure | 1200 | m2 @ | £23 |
| Upper Floors | 100 500 | 12.72 | 1.14 |
| Prestressed, precast concrete structural suspended floor units; 50 mm thick structural topping | 1400 | m2 @ | £70 |
| Extra for 7.5 kN/m2 floor loading to plant room areas | 500 | m2 @ | £5 |
| Roof | 424 000 | 53.67 | 4.81 |
| Roof cladding; curved; raised-seam aluminium roofing; cladding; structural deck; insulation; vapour barrier; soffit lining | 6800 | m2 @ | £40 |
| Extra for rooflights; double-skin polycarbonate; including framing and secondary steelwork; sunshading | 200 | m2 @ | £260 |
| Allowance for automatic smoke vents to stairwells | item | @ | £4,000 |
| Allowance for work to boundaries, gutters, rooflights, openings and so on | 1050 | m @ | £20 |
| Entrance canopy; hollow-section framing; structural glazing; complete | item | @ | £30 000 |
| Allowance for roof safety system | 500 | m @ | £90 |
| Stairs | 43 000 | 5.44 | 0.49 |
| Precast concrete stairs and half landings; overall rise 4 m; stainless steel handrails; finishes | 1 | @ | £10 000 |
| Precast concrete stairs and half landings; overall rise 4 m; polyester-powder-coated steel handrails; finishes | 1 | @ | £8,000 |
| Allowance for access platforms and stairs to plant rooms | item | @ | £20 000 |
| Allowance for roof access, stairs and hatches | item | @ | £5,000 |
| External walls, windows and doors | 721 500 | 91.33 | 8.18 |
| Curtain walling; framed double-glazed units; colour coated aluminium framing; flashings; accessories | 660 | m2 @ | £250 |
| Wall cladding; colour-coated aluminium; smooth-faced composite panels; flashings; accessories | 2025 | m2 @ | £200 |
| Extra for aluminium-framed, thermally broken window units; sealed double-glazed units; 30% opening lights | 200 | m2 @ | £100 |
| Extra for glazed entrance screen; two fully glazed double doorsets; ironmongery and accessories | 50 | m2 @ | £300 |
| Extra for louvre panels to plant areas; colour coated | 200 | m2 @ | £100 |
| Sunshading to windows and curtain walling | 250 | m @ | £250 |
| High-security steel double doors and frames; colour coated; ironmongery; accessories | 16 | @ | £2,000 |
| Sectional doors to loading bay; electrically operated; 2.4 × 2.7 m; including controls | 7 | m2 @ | £280 |
| Internal walls and partitions | 351 800 | 44.53 | 3.99 |
| Insitu concrete shear walls; average 215 mm thick | 200 | m2 @ | £75 |
| Blockwork partitions; 215 mm average thickness, 140 mm blocks laid on side; head restraint | 1300 | m2 @ | £38 |
| Metal stud partitions; two layers wallboard, each side; insulation | 3100 | m2 @ | £35 |
| Demountable partitions; monobloc with fully glazed office fronts; including doors, ironmongery and accessories | 1350 | m2 @ | £110 |
| WC cubicle partitions | 40 | @ | £600 |
| Melamine-faced solid laminate access panelling to WCs and so on | 80 | @ | £80 |
| Cost breakdown | |||
| element cost £ | £/m2 gifa | % of total cost | |
| Internal doors | 104 000 | 13.16 | 1.18 |
| Flush doors; fire-rated; solid-core veneer-faced; hardwood frames; ironmongery; complete | 55 | @ | £650 |
| Flush doors; non-fire-rated; solid-core veneer-faced; hardwood frames; ironmongery; complete | 115 | @ | £550 |
| Allowance for services access panels | item | @ | £5,000 |
| Wall finishes | 114 400 | 14.48 | 1.30 |
| Independent wall lining; plasterboard lining to inner face of external walls; two coats emulsion paint | 2500 | m2 @ | £14 |
| Drylining; plasterboard to internal masonry walls; two coats emulsion paint | 1500 | m2 @ | £9 |
| Two coats emulsion paint; to plasterboard partitions | 4050 | m2 @ | £3 |
| Ceramic tiles; sand cement backing to plasterboard | 460 | m2 @ | £40 |
| Vinyl wall finish to plasterboard | 1100 | m2 @ | £8 |
| Extra for enhanced quality applied finishes in rest areas | 260 | m2 @ | £12 |
| Two coats emulsion paint/dust sealer to blockwork | 1300 | m2 @ | £3 |
| Hygienic finishes to kitchen areas; laminate panels | 325 | m2 @ | £60 |
| Floor finishes | 525 000 | 66.46 | 5.96 |
| Natural stone flooring, including allowances for screeds and skirtings to reception area | 50 | m2 @ | £100 |
| Allowance for mats and matwells | item | @ | £5,000 |
| Raised access floor; 500 mm deep floor void; including allowances for cavity barriers | 6650 | m2 @ | £42 |
| Extra for seals to form airtight plenum, for forming holes in floor tiles and for fixing free issue supply air diffusers | 6500 | m2 @ | £4 |
| Heavy-duty carpet tiles; including allowance for cutting holes for floor diffusers and skirtings to raised floor tiles | 6500 | m2 @ | £27 |
| Anti-static vinyl floor tiles; bonded to raised floor tiles; including allowances for cutting holes for floor diffusers and skirtings | 150 | m2 @ | £18 |
| Vinyl floor tiles; including allowance for screed and skirtings; to WCs and kitchen areas | 400 | m2 @ | £27 |
| Semi-sprung beech strip flooring; including allowance for skirtings; to aerobics/gym | 100 | m2 @ | £60 |
| Concrete hardener to raised floor plenums and plant rooms | 7350 | m2 @ | £2 |
| Ceiling Finishes | 96 800 | 12.25 | 1.10 |
| Suspended ceilings; mineral fibre tiles; semi-concealed grid; to office and support areas | 3150 | m2 @ | £26 |
| Extra for moisture-resistant mineral fibre tiles to WCs | 250 | m2 @ | £5 |
| Extra for acoustic tiles to aerobics areas/gym | 100 | m2 @ | £5 |
| Suspended ceilings, hygienic metal tiles to kitchen areas | 250 | m2 @ | £40 |
| Extra for enhanced ceiling finishes to reception, dining and rest areas | 315 | m2 @ | £10 |
| Furniture and fittings | 255 600 | 32.35 | 2.90 |
| Reception desk and fittings | item | @ | £10 000 |
| Allowance for furniture and fittings to dining areas | item | @ | £50 000 |
| Allowance for fixed equipment to gym/aerobics areas | item | @ | £10 000 |
| Allowance for fittings; lockers, coat racks, shelves and so on | item | @ | £70 000 |
| Statutory and directional signage | item | @ | £10 000 |
| Allowance for decorative features, banners, graphics and so on to call centre areas | item | @ | £100 000 |
| Window blinds | 140 | m2 @ | £40 |
| Sanitary fittings | 33 900 | 4.29 | 0.38 |
| WCs, urinals, wash-hand basins; generally | 105 | @ | £250 |
| Allowance for fittings for disabled WCs | item | @ | £1,000 |
| Showers; cabinets; trays; fittings | 6 | @ | £1,000 |
| Cleaners’ sinks | 3 | @ | £200 |
| Services equipment | 300 000 | 37.97 | 3.40 |
| Catering installation complete; kitchen equipment; dishwash installation; servery fit-out | item | @ | £300 000 |
| Disposal installations | 59 300 | 7.51 | 0.67 |
| Rainwater disposal; cast iron downpipes and fittings | 7900 | m2 @ | £3.50 |
| Waste, soil and vent installation; PVCu pipework and fittings | 7900 | m2 @ | £4 |
| Water installations | 45 000 | 5.70 | 0.51 |
| Hot and cold-water service; calorifiers; hot and cold-water storage; distribution | 150 | @ | £300 |
| Cost breakdown | |||
| element cost £ | £/m2 gifa | % of total cost | |
| Space heating and air treatment | 1 652 300 | 209.15 | 18.74 |
| Gas installation | item | @ | £20 000 |
| Low-temperature hot-water heating; boiler plant (900 kW); stainless steel flues; pumps and valves; distribution within plant rooms; insulation | 7900 | m2 @ | £7.50 |
| Perimeter heating; trench heating installation | 7900 | m2 @ | £12 |
| Chilled water installation; chillers and heat rejection (total load 2300 kW); pressurisation unit; pumps and valves; distribution within plant rooms; insulation and trace heating | 7900 | m2 @ | £80 |
| Supply and extract ventilation; air-handling units; heating, cooling and reheat coils; ductwork in risers and plant rooms | 7900 | m2 @ | £28 |
| Supply and extract ventilation; displacement system; ductwork; supply-only floor diffusers | 6500 | m2 @ | £30 |
| Supplementary cooling; two-pipe fan-coil installation to cellular space; chilled-water distribution; condensate drainage; fan-coil units; ductwork; insulation; grilles and diffusers | 2900 | m2 @ | £90 |
| Dedicated cooling to communications room; including back-up provision | item | @ | £50 000 |
| WC extract installation | 7900 | m2 @ | £5 |
| Kitchen supply and extract installation | item | @ | £40 000 |
| Allowance for smoke extract at roof level | 7900 | m2 @ | £5 |
| Electrical installations | 611 500 | 77.41 | 6.94 |
| Allowance for heating and ventilating installation; 1 MW transformer; HV switchgear | item | @ | £40 000 |
| Mains and submains installation | 7900 | m2 @ | £20 |
| Small power distribution | 7900 | m2 @ | £8 |
| Extra for enhanced small power to call centre floor and training rooms | 4000 | m2 @ | £20 |
| Lighting and luminaires to call centre floor | 3700 | m2 @ | £35 |
| Lighting and luminaires to offices, support space and rest areas | 1650 | m2 @ | £45 |
| Lighting and luminaires to plant rooms | 700 | m2 @ | £10 |
| Emergency lighting installation | 7900 | m2 @ | £5 |
| Power to mechanical services | item | @ | £20 000 |
| Standby generation; small power, lighting and essential services, 2 @ 1500 kVA; providing 100% redundancy; excluded as part of end-user fit-out | Excluded | ||
| Uninterruptable-power supply; small power and essential services, 4 @ 500 kVA; providing 100% redundancy; excluded as part of end-user fit out | Excluded | ||
| Lift installations | 40 000 | 5.06 | 0.45 |
| Eight-person, electro-hydraulic lift serving two floors; 0.6 m/s | 1 | @ | £40 000 |
| Protective installations | 51 600 | 6.53 | 0.59 |
| Lightning protection | 7900 | m2 @ | £2 |
| Earthing and bonding | 7900 | m2 @ | £2 |
| Fire suppression installation to communications room; Inergen | item | @ | £20 000 |
| Communications installations | 875 000 | 110.76 | 9.92 |
| Fully addressible fire and smoke detection and alarm system | 7900 | m2 @ | £18 |
| Public address system | 7900 | m2 @ | £10 |
| Intruder detection | 7900 | m2 @ | £5 |
| Allowance for security, closed-circuit television and access control | 7900 | m2 @ | £15 |
| Turnstile entry control with card operation | item | @ | £50 000 |
| Wireways for telephones, data and structured cable | 7900 | m2 @ | £5 |
| Structured cabling; providing eight comms ports per work station | 6250 | m2 @ | £65 |
| Special installations | 237 000 | 30.00 | 2.69 |
| Building management system | 7900 | m2 @ | £30 |
| Builder’s work in connection | 117 000 | 14.81 | 1.33 |
| Forming holes, chases and so on, allow 3% | item | @ | £117 000 |
| Preliminaries and contingencies | 1 150 000 | 145.57 | 13.04 |
| Contractor’s overheads, site establishment and site supervision, allow 10% | item | @ | £767 000 |
| Contingency sum, allow 5% | item | @ | £383 000 |
| Total construction cost (building only) | 8 816 300 | 1 115.98 | 100 |
| Regional variations | |
| Costs in this article are based on a scheme in the Midlands and should be adjusted by the following location factors for projects in other areas. | |
| Inner London | 1.20 |
| Outer London | 1.14 |
| South-east | 1.07 |
| South-west | 1.03 |
| East Anglia | 1.02 |
| Yorkshire and Humberside | 1.00 |
| North-west | 1.06 |
| North | 1.01 |
| Scotland | 1.01 |
| Wales | 1.00 |
| Northern Ireland | 0.86 |