| Elemental cost analysis | |||||
| Total cost of element (£) gross floor area | % of total cost | Cost/m2 of 1026 m2 | Quantity | Unit cost of element (£) | |
| Preliminaries | 132 330 | 13.45 | 128.98 | – | – |
| Substructure | 116 530 | 11.85 | 113.58 | 595 m2 | 195.85/m2 |
| Frame | 62 460 | 6.35 | 60.88 | 1 026 m2 | 60.88/m2 |
| Upper floors | 47 400 | 4.82 | 46.2 | 431 m2 | 109.98/m2 |
| Roof | 87 100 | 8.86 | 84.89 | 748 m2 | 116.44/m2 |
| Stairs | 9 450 | 0.96 | 9.21 | 2 nr | 4 725.00 |
| External walls | 41 530 | 4.22 | 40.48 | 557 m2 | 74.56/m2 |
| Windows and external doors | 59 600 | 6.06 | 58.09 | 235 m2 | 227.96/m2 |
| Internal walls and partitions | 24 760 | 2.52 | 24.13 | 497 m2 | 49.82/m2 |
| Internal doors | 9 640 | 0.98 | 9.4 | 21 nr | 459.05 |
| Wall finishes | 13 470 | 1.37 | 13.13 | 1285 m2 | 10.48 m2 |
| Floor finishes | 41 060 | 4.17 | 40.02 | 1014 m2 | 40.49/m2 |
| Ceiling finishes | 42 070 | 4.28 | 41 | 1073 m2 | 39.21/m2 |
| Fixtures and fittings | 16 190 | 1.65 | 15.78 | – | – |
| Sanitary appliances | 13 860 | 1.41 | 13.51 | – | – |
| Disposal installation | 1 170 | 0.12 | 1.14 | – | – |
| Water installation and heat source | 51 090 | 5.19 | 49.8 | – | – |
| Electrical installation | 80 130 | 8.15 | 78.1 | – | – |
| Gas installation | 5 000 | 0.51 | 4.87 | – | – |
| Lift installation | 12 940 | 1.32 | 12.61 | – | – |
| Builder’s work | 4 300 | 0.44 | 4.19 | – | – |
| External works | 78 610 | 7.99 | 76.62 | – | – |
| Drainage | 32 900 | 3.34 | 32.07 | – | – |
| Amount of final account | 983 590 | 100 | 958.66 | – | – |
| Key technical data | |
| Roof U-value: | 0.13 W/m2°C |
| Walls U-value: | 0.26 W/m2°C |
| Window U-value (mid-pane): | 1.9 W/m2°C |
| Heating demand: | less than 50 W/m2 of floor area |
| Lighting energy use: | less than 10 W/m2 |
| Target carbon dioxide emission: | 40 kg/m2/year |