| Hot rates | ||||
| Unit | Typical £ | Keen £ | Rate move | |
| Groundwork and excavations | ||||
| Excavate to reduce levels 1 m maximum depth | m3 | 1.25 | 0.9 | Down |
| Excavate trench 1 m maximum depth | m3 | 5.15 | 4.3 | Down |
| Backfilling with granular fill | m2 | 17.5 | 16 | Down |
| Extra for breaking out reinforced concrete | m3 | 20.75 | 14.75 | Down |
| Remove excavated material from site | m3 | 12.4 | 9.6 | Down |
| Hardcore in making up levels | m3 | 19 | 15 | Down |
| In situ concrete | ||||
| Plain concrete foundations | m3 | 58 | 54 | Up |
| Reinforced concrete foundations | m3 | 66 | 61.5 | Up |
| Basic formwork to 250 mm foundation | m | 6.6 | 5.1 | Up |
| Basic formwork to walls | m2 | 25.35 | 22 | Down |
| High yield bar reinforcement, 16 mm diameter | tonne | 575 | 510 | Up |
| Mesh, 2.22 kg/m2 (A142) | m2 | 1.65 | 1.5 | Up |
| Mesh, 3.02 kg/m2 (A193) | m2 | 2.95 | 2.3 | Up |
| Polythene sheeting | m2 | 0.6 | 0.55 | No change |
| Masonry | ||||
| Facing bricks (machine-made) for wall | m2 | 36.85 | 35 | Up |
| Dense aggregate precast concrete block walls/partitions - 100mm | m2 | 15 | 12.15 | Up |
| 140 mm | m2 | 19.8 | 15.5 | Up |
| 50 mm cavity batts | m2 | 2.65 | 2.05 | Down |
| Structural steel framing | ||||
| Fabricated steelwork Grade 43 universal beams or columns, erected (less then 50 tonnes) | tonne | 1130 | 925 | Up |
| Carpentry | ||||
| Treated sawn softwood - wall or partition member 50 × 100 mm | m | 2.4 | 2.1 | Up |
| pitched roof member 50 × 150 mm | m | 3.4 | 3.15 | Up |
| 19 mm butt jointed plywood flooring | m2 | 15 | 14 | Up |
| Joinery | ||||
| Wrot softwood - 32 × 125 mm door lining | m | 9.35 | 9.1 | Up |
| 19 × 50 mm architrave, splayed | m | 4.2 | 3 | Up |
| 19 × 150 mm skirting, splayed | m | 3.85 | 3.55 | Up |
| Roofing | ||||
| Concrete interlocking roof tiles | m2 | 14.5 | 13 | Up |
| Artificial slates | m2 | 22.5 | 20.5 | No change |
| Plastering and screeding | ||||
| 75 mm thick floor screed | m2 | 9.75 | 8 | No change |
| 13 mm lightweight plaster | m2 | 7.25 | 6.75 | Up |
| Galvanized mild steel angle bead | m | 1.4 | 1.1 | Up |
| 3 mm skim on 12.5 mm baseboard to ceilings | m2 | 9.5 | 8.25 | Up |
| Ceramic tiling | ||||
| Ceramic wall tiles, plain colours | m2 | 29.45 | 27.5 | Down |
| 2 mm vinyl sheet | m2 | 14.8 | 14.6 | Down |
| Painting | ||||
| Mist and two coats emulsion on plaster | m2 | 2.15 | 1.75 | Down |
| KPS & three coats on wood | m2 | 4.75 | 4.6 | Down |
| Prime and three coats on metal | m2 | 5.4 | 4.9 | Down |
| Glazing | ||||
| 4 mm clear float glass bradded in | m2 | 22.1 | 22 | No change |
| Holes for services | ||||
| Hole for pipe not exceeding 55 mm diameter through 100 mm blockwork | nr | 2.5 | 2.1 | Up |
| Insulation | ||||
| 200 mm mineral-fibre mat between members | m2 | 5 | 3.25 | Up |
| External works | ||||
| Granular material type 1 to make up levels | m3 | 24 | 18.5 | Down |
| Imported topsoil to make up levels | m3 | 13 | 12 | Down |
| Precast concrete paving slabs, coloured, textured, 50 mm thick, sand bed | m2 | 15.5 | 12.35 | Down |
| Fencing | ||||
| Softwood close boarded fencing 1800 mm high | m | 32.5 | 31 | Down |
| Foul drainage above ground | ||||
| 32 mm PVCu waste pipe plugged and screwed | m | 3.75 | 3.5 | Down |
| 110 mm PVCu soil pipe plugged and screwed | m | 9.5 | 8.5 | Down |
| Drainage below ground | ||||
| Excavate pipe trench 1500 mm average depth - backfill with earth | m | 13.5 | 13 | Down |
| backfill with granular material | m | 37 | 35 | Down |
| Granular bed and surround to - 100 mm dramatic pipe | m | 5.25 | 4.4 | Up |
| 150 mm diameter pipe | m | 7 | 6 | Up |
| Concrete bed and surround to 100 mm pipe | m | 14.3 | 10.3 | Up |
| 100 mm clay drain pipe with flexible couplings | m | 4.2 | 3.9 | No change |
| Key indicators and materials prices | |
| Percentage change over past 12 months (provisional to Sept 1999) | |
| Key indicators | |
| Retail prices index | |
| Headline rate (RPI) | 1.1 |
| All items excluding mortgage interest payments (RPIX) – government’s target index | 2.1 |
| All items excluding mortgage interest payments and indirect taxes (RPIY) | 1.3 |
| Construction industry | |
| Construction materials | -1.9 |
| Housebuilding materials | -1.1 |
| Mechanical machinery and equipment | 1.4 |
| Electrical machinery and apparatus | -1.7 |
| Source: Office for National Statistics (September 1999 figures are provisional) | |
| Regional variations | ||
| % variation from outer London | % adjustment to Spon’s major works section | |
| Outer London | 0 | –7 |
| Inner London | 9 | 2 |
| East Anglia | –12 | –18 |
| East Midlands | –16 | –21 |
| North | –16 | –21 |
| Northern Ireland | –33 | –38 |
| North-west | –13 | –19 |
| Scotland | –13 | –19 |
| South-east | –4 | –10 |
| South-west | –12 | –18 |
| Wales | –17 | –23 |
| West Midlands | –17 | –23 |
| Yorkshire/Humberside | –15 | –21 |
| Electricians’ wage agreement 2000-2001 | ||||||
| National standard rates | With London weighting | |||||
| Shop reporting | Job reporting | Shop reporting | Job reporting | |||
| transport provided | own transport | transport provided | own transport | |||
| Technician | £8.94 | £9.27 | £9.49 | £9.46 | £9.81 | £10.04 |
| Approved electrician | £7.82 | £8.15 | £8.37 | £8.34 | £8.69 | £8.92 |
| Electrician | £7.13 | £7.46 | £7.68 | £7.65 | £8.00 | £8.22 |
| Labourer | £5.52 | £5.85 | £6.07 | £6.04 | £6.39 | £6.62 |
| Senior graded electrical trainee | £6.42 | £6.71 | £6.91 | £6.94 | £7.23 | £7.43 |
| Adult trainee | £5.52 | £5.85 | £6.07 | £6.04 | £6.39 | £6.62 |
| Adult trainee (under 21) | £4.14 | £4.39 | £4.55 | £4.66 | £4.91 | £5.07 |
| ECIBA credit values and electrical apprentices’ rates | |||
| Grade | Weekly credit values | Holiday portion | Suggested “top-up”* |
| Technician | £35.52 | £28.37 | £15.07 |
| Approved electrician | £31.96 | £24.81 | £13.79 |
| Electrician | £29.77 | £22.62 | £12.95 |
| Labourer | £24.67 | £17.52 | £11.13 |
| Senior graded electrical trainee | £27.52 | £20.37 | £11.78 |
| Adult trainee | £24.67 | £17.52 | £11.13 |
| Trainee under 21 | £20.29 | £13.14 | £8.80 |
| Apprentices’ hourly rates (London) | |||
| Junior apprentice | £2.61** | ||
| Senior apprentice (stage one) | £3.70 | ||
| Senior apprentice (stage two; one year’s experience) | £5.67 | ||
| * Figures have been calculated by DL&E based on the Electrical Contracting Industry Benefits Agency “top-up” holiday funding example. | |||
| ** The National Minimum Wage rates will increase this to £3.00 an hour for for 18-21 year olds. | |||
| Build-up of the annual cost of a notional 11-person gang (London weighting) | ||||
| Technician (1) | Approved electricians (4) | Electricians (6) | Subtotal | |
| £ | £ | £ | £ | |
| Hourly rate from 7 February 2000 | 10.04 | 8.92 | 8.22 | |
| Working hours a year | 1725 | 6900 | 10350 | |
| £/year | 17 921.40 | 63 688.80 | 88 036.20 | 169 646.40 |
| Incentive scheme @ 5% | 896.07 | 3 184.44 | 4 401.81 | 8 482.32 |
| Daily travelling time allowance | 4.54 | 4.54 | 4.54 | |
| Daily travel allowance | 2.13 | 2.13 | 2.13 | |
| £/year | 1 534.10 | 6 136.40 | 9 204.60 | 16 875.10 |
| JIB combined benefits scheme (weeks) | 52 | 208 | 312 | |
| Benefit credit value | 35.52 | 31.96 | 29.77 | |
| Top-up funding for WTD (optional) | 17.24 | 15.72 | 14.73 | |
| £/year | 2 743.52 | 9 917.44 | 13 884.00 | 26 544.96 |
| National Insurance contributions | ||||
| Weekly gross pay (subject to NI) each | 434.88 | 389.45 | 361.05 | |
| £ contributions (12.2% above £83 a week) | 42.93 | 37.39 | 33.92 | |
| £ contributions/year | 1 974.78 | 6 879.15 | 9 362.52 | 18 216.45 |
| Total per year | 239 765.23 | |||
| Training, including any trade registrations (1%) | 2 397.65 | |||
| Severance pay and sundry costs (1.5%) | 3 596.48 | |||
| Employers liability and third-party insurance (2%) | 4 795.30 | |||
| Annual cost of notional 11-person gang (10.5 people actually working) | 250 554.66 | |||
| Annual cost per productive person | 23 862.35 | |||