| Charge-out rates by role (£/h) | |||
| lowest | median | upper | |
| Sole principal | 26 | 35 | 50 |
| Partner/director | 40 | 50 | 60 |
| Associate | 35 | 40 | 50 |
| Senior surveyor | 30 | 35 | 40 |
| Surveyor | 20 | 25 | 32 |
| Postgraduate/junior surveyor | 15 | 20 | 25 |
| Average fees in different sectors as a percentage of construction cost | |
| Leisure | |
| New build, JCT contract | 2.5 |
| New build, design-and-build contract | 2.3 |
| Refurbishment, JCT contract | 2.7 |
| Refurbishment, design-and-build contract | n/a |
| Office | |
| New build, JCT contract | 2.2 |
| New build, design-and-build contract | 1.6 |
| Refurbishment, JCT contract | 3.8 |
| Refurbishment, design-and-build contract | 2.9 |
| Industrial | |
| New build, JCT contract | 2.3 |
| New build, design-and-build contract | 2.1 |
| Refurbishment, JCT contract | 2.3 |
| Refurbishment, design-and-build contract | n/a |
| Public housing | |
| New build, JCT contract | 2.6 |
| New build, design-and-build contract | 1.4 |
| Refurbishment, JCT contract | 4.2 |
| Refurbishment, design-and-build contract | n/a |
| Fees per type of contact as a percentage of construction cost | |
| New build, JCT | |
| Contract value | Fees (%) |
| £2m | 2.3 |
| £4m | 2.1 |
| £6m | 2.0 |
| £8m | 1.9 |
| £10m | 1.9 |
| £12m | 1.8 |
| £14m | 1.8 |
| £16m | 1.8 |
| £18m | 1.8 |
| £20m | 1.7 |
| New build, design and build | |
| Contract value | Fees (%) |
| £2m | 1.9 |
| £4m | 1.8 |
| £6m | 1.7 |
| £8m | 1.7 |
| £10m | 1.6 |
| £12m | 1.6 |
| £14m | 1.5 |
| £16m | 1.5 |
| £18m | 1.5 |
| £20m | 1.5 |
| Refurbishment, JCT | |
| Contract value | Fees (%) |
| £1m | 2.8 |
| £2m | 2.4 |
| £3m | 2.2 |
| £4m | 2.1 |
| £5m | 1.9 |
| Refurbishment, design and build | |
| Contract value | Fees (%) |
| £1m | 2.3 |
| £2m | 2.2 |
| £3m | 2.1 |
| £4m | 2.1 |
| £5m | 2.0 |