| Capital costs for the three options | |||
| Option 1 (£) | Option 2 (£) | Option 3 (£) | |
| Renew or refurbish escalators | 350 000 | 750 000 | 350 000 |
| Re-clad escalators | 100 000 | included in above | 100 000 |
| Strip out existing escalators | N/A | 50 000 | N/A |
| Remove and reinstate facade for escalator removal | N/A | 20 000 | N/A |
| Miscellaneous building works | 9 700 | 28 800 | 9 700 |
| New power supplies | 14 500 | 14 500 | 14 500 |
| Testing, commissioning and subcontract preliminaries | 23 710 | 43 165 | 23 710 |
| Sub-total – new installation works | 497 910 | 906 465 | 497 910 |
| Main contractor’s preliminaries, overheads, profit and attendance | 87 134 | 158 631 | 87 134 |
| Builders work in connection | included | included | included |
| Professional fees | 59 749 | 108 776 | 59 749 |
| Sub-total | 644 793 | 1 173 872 | 644 793 |
| Less capital allowances relief | (159 783) | (290 973) | (159 783) |
| Total capital cost | 485 011 | 882 899 | 485 011 |