| Elemental cost analysis | |||||
| Tender cost | Tender cost | % of total | Out-turn cost | Out-turn cost | |
| £ | £/m2 | tender cost | £ | £/m2 | |
| Substructure (including floor slab) | 155,259 | 57 | 7.7 | 168,456 | 61 |
| Superstructure | 598,220 | 218 | 29.6 | 649,069 | 236 |
| Finishes | 175,895 | 64 | 8.7 | 190,846 | 69 |
| Fittings and furnishings | 282,630 | 103 | 14 | 306,654 | 112 |
| Services | 354,985 | 130 | 17.6 | 385,159 | 140 |
| (electrical installations, gas installations, lifts and conveyor installations, communications | |||||
| installations, builders’ work in connection with services and builders’ project and attendance on services) | |||||
| External works | 228,792 | 83 | 11.3 | 248,239 | 90 |
| Preliminaries | 150,901 | – | 7.5 | 163,728 | – |
| Design fees | 71,800 | – | 3.6 | 77,903 | – |
| Total | 2,018,482 | 791 | 100 | 2,190,053 | 798 |