| Local authority | Original expected project completion date | Current expected project completion date | Major reasons for delay |
| Bradford | Dec-07 | Sep-08 | Challenging original completion expectations; Issues around use of untested processes |
| Bristol | Apr-08 | Jan-09 | Challenging original completion expectations; Issues around use of untested processes |
| Greenwich | Apr-09 | Sep-11 | Piloting of non-standard BSF procurement model by local authority has been problematic and has caused considerable delay; Local resourcing difficulties; Issues around use of untested processes |
| Knowsley | Sep-09 | Jan-10 | Issues around use of untested processes |
| Leeds | Sep-10 | Sep-11 | Issues around use of untested processes |
| Lewisham | Jul-10 | Sep-10 | Issues around use of untested processes |
| Manchester | Sep-09 | Jun-11 | Challenging original completion expectations; Issues around use of untested processes; later project rescoping, including integrating seven new academies |
| Newham | Jan-09 | Mar-11 | Challenging original completion expectations; Issues around use of untested processes; Local resourcing difficulties |
| Sheffield | Mar-10 | Apr-11 | Challenging original completion expectations; Issues around use of untested processes |
| Solihull | Sep-08 | Sep-09 | Challenging original completion expectations; Issues around use of untested processes |
| STaG | Dec-12 | Jan-13 | Issues around use of untested processes |
| Sunderland | Jan-10 | Sep-10 | Challenging original completion expectations; Issues around use of untested processes |
| Local authority | Original expected project completion date | Current expected project completion date | Major reasons for delay |
| Birmingham | Sep-10 | Sep-11 | Challenging original completion expectations; Local resourcing difficulties; More time taken to develop transformational strategy; later project rescoping, including integrating new academies |
| Hackney | Sep-13 | Nov-13 | Issues around use of untested processes |
| Haringey | Mar-11 | Oct-11 | Issues around use of untested processes |
| Islington | Sep-11 | Sep-12 | Local resourcing difficulties; More time taken to develop transformational strategy |
| Liverpool | Sep-10 | Sep-11 | Local resourcing difficulties; More time taken to develop transformational strategy; Issues around use of untested processes; Piloting of non-standard BSF procurement model by local authority has caused some delay |
| Middlesbrough | Sep-11 | Sep-12 | Local resourcing difficulties; changes to procurement strategy to achieve a better value for money outcome caused some delay |
| Tower Hamlets | Jun-11 | Dec-11 | Local resourcing difficulties; More time taken to develop transformational strategy |
| Local authority | Original expected project completion date | Current expected project completion date | Major reasons for delay |
| Luton | Sep-10 | Nov-12 | Local resourcing difficulties; Issues around identifying new sites for new schools have caused delay to the project |
| N Lincs | Jun-11 | Apr-12 | Local resourcing difficulties; More time taken to develop transformational strategy |
| Salford | Jan-12 | Sep-12 | More time taken to develop transformational strategy |
| Sandwell | Mar-11 | Jul-11 | More time taken to develop transformational strategy |
| Tameside | Jan-11 | Feb-11 | More time taken to develop transformational strategy |