By Tony Bingham2020-01-21T09:34:00
Adjudicators need not give detailed reasons for their decisions – and can use a little help without accounting for that either
When the adjudicator’s fee account came in for Babcock Marine (Clyde) Ltd vs HS Barrier (Coatings) Ltd, it included 28 hours of QS assistance. Foul, shouted one of the parties at the adjudicator; the decision in the award is tainted, unenforceable, because you didn’t tell us of any helper, nor what they were doing. This, said the party, is a breach of natural justice.
Their pointy stick jabbed at the NEC adjudicator contract document, in particular at clause 2.3 therein. This clause wails at the adjudicator that they can seek whatever help they consider necessary from others but must pipe up and say so – and then, once this little helper helps, the adjudicator must provide the parties with a copy of any information or advice from others and write their comments on it.
Read more …
Existing subscriber? LOGIN
Stay at the forefront of thought leadership with news and analysis from award-winning journalists. Enjoy company features, CEO interviews, architectural reviews, technical project know-how and the latest innovations.
Get your free guest access SIGN UP TODAY
Subscribe to Building today and you will benefit from:
View our subscription options and join our community