As the Royal Festival Hall closes this week ready for work to begin on its refurbishment, other elements of the South Bank Centre redevelopment master plan are being worked out. Michael Willoughby reports on the work so far on a project with a unique set of challenges

When, in 1949, Robert Matthew, Leslie Martin, Peter Moro and Edwin Williams planned the Royal Festival Hall, which closed for an 18-month refurbishment on Friday, they were faced with a tight site indeed for a “people’s palace”.

The building, housing a 3,165-seat auditorium and London’s largest dance floor, had to fit on a 200ft2 site, hemmed in by the river, the Hungerford Railway Viaduct and the site for Lasdun’s planned National Theatre.

Mike Elks, project engineer with Taylor Woodrow, could only dream of such space when it came to adding an extension immediately next door. The four storey building, containing second and third floor staff offices intended to free up space in the RFH and ground floor retail, was designed by Allies & Morrison.

The proximity of the site to the main London to Kent and Sussex railway line has forced Elks and his team to resort to unusual methods when adding the skin of the building. The greatest risk came from a signal, which must be visible at all times, sited two inches from the outside wall and even dictated the design of the skin. This was originally designed at full elevation height to be pivoted into place from the ground, but later revised to comprise prefabricated unified panelling. This panelling will now be swung from the shorter side of the building around the corner on a monorail and dropped into place on the railway-facing side. The ½ tonne, 1.7m-wide, units will be restrained by steel rope to prevent them getting into the path of the railway.

The danger of objects falling from the overhang onto highly-trafficked areas has also meant that tower cranes could not be used. The steel frame, which took three months to construct, was built using scissor lifts.

All this explains why, even though the building is little more than a sleekly detailed box, its project planning and risk management have stretched even a man as experienced as Elks, who oversaw much of the recent work on the Heathrow Express. He calls it the most challenging and enjoyable project he has ever worked on. And it’s not just the trains the team needs to worry about. Altogether, six million people pass by the site annually, including commuters, on the rat run between Charing Cross and Embankment stations and Waterloo, and tourists walking around the largest arts centre in the world and from the London Eye to the Tate Modern.

A main potential cost hindrance – possession orders, which would have seen trains on the rail line stopped during designated hours – has been avoided due to solutions put in place by project managers, Bovis Lend Lease. Collaboration with Network Rail began six months before the project started in February and remained close throughout, with the track operators keeping a presence on site throughout construction. The train operators were even responsible for approving the new skin installation method.

Difficulties in building the RFH extension were compounded by the site having only one access point, meaning that everything had to be built from one end to the other.

But if the nearby railway provided headaches during construction, failing to take account of its potential effect on residents would have proved disastrous in perpetuity. The Royal Festival Hall was built with double concrete walls to prevent the sound of trains from ruining concerts. For the modern, steel framed extension, a modern solution had to be found. So, to eliminate vibrations, the structure was built on a grid of concrete longitudinal and traverse ground beams. These rested on pile caps under which are elastometric bearings, more typically used to reduce the effect of earthquakes on buildings. The extension does not touch the ground or the bridge. To bring noise levels to within health and safety standards, Paul Harding, in charge of interface design production for Taylor Woodrow, worked to find the optimum sized floor area and thinnest low-frequency acoustic wall that would block out train noise while maximising office space. To make matters yet more interesting, Network Rail told Harding that trains rumbled at different frequencies depending on the age and model.

Another key factor in pre-work cost planning was allowing for the uncertain nature of a much excavated riverside site. Richard Baldwin, from the project’s QS Davis Langdon, feared the surveys were not to be trusted and established a contingency sum in the budget that would take account of unknowns during the build. He was proved prudent when an unmarked six-foot deep piece of concrete was discovered and had to be incorporated into plans.

Taylor Woodrow and partners are pleased at how the project is progressing. Risk and project management have played a larger than usual part in the process. Even with all the work done upfront, Elks estimates that the site restrictions imposed 30-40% higher costs and 30% higher duration on the project.

Davis’ Baldwin points out that overruns were minimised thanks to the simple nature of the building.

It is no coincidence that Taylor Woodrow had managed the Royal Albert Hall restoration project. During foundation laying at RFH, care was also taken to avoid rehearsal and concert times. Construction, transportation and music could then take place together in near-absolute harmony.

Planned project duration 76 weeks
Contract sum 11,266,000
Gross internal area 53,840 ft
Cost per FT2 £209
Cost includes shell and core plus Cat A.

Retail is shell only.

Cost includes external work.

Single stage design and build contact using GC/works contract.

Enter stage right

South Bank Centre masterplan

The extension building for the RFH is just one aspect of a SBC due to change radically within the next few years, the boldest of these alterations being the physical layout of the arts complex. American architect, Rick Mather, glass fan and adherent of Jane Jacobs, has taken up the challenge by which so many before him, including Terry Farrell and Richard Rogers, had been defeated. Mather has plans to reorganise the currently bewildering site by bringing all entrances down to ground level, making all frontages active, and taking service routes out of the public realm.
Other changes to the SBC including the two, new squares, are laid out below. The project is notably heavy in retail and catering establishments, rendering the project nearly self-financing. If the SBC does not end up looking too much like a mall, this extra traffic could actually help counteract the perceived barrenness of the site.

Royal Festival Hall

The RFH closed for an 18-month refurbishment on Friday with £10m in funding – or a third of required – still to find and a public appeal under way. Main works comprise improving the acoustics and installing comfier seats with more legroom.

Landscaping

Gross Max, architects for Bilbao and the Birmingham Bullring will begin work shortly on the areas surrounding Hall, including Festival Square and River Link Square – the area between the RFH and Hayward Gallery/Queen Elizabeth Hall.

Waterfront

The riverside will be spruced up with much inspiration coming from the 1951 Festival of Britain, including a new granite staircase reflecting the curve of the RFH and river.

Lighting

New lighting schemes have been mooted, such as blue LED lights in the trees on Queen’s Walk, highlighting of the balcony edge, riverside terrace and the canopies, the Hungerford Terrace, Waterloo Entrance and auditorium roof.

Terraces

On Hungerford Terrace limestone paving will extend the RFH foyer into the granite surface of the terrace. The Riverside Terrace will have seating and a canopy over the new outdoor staircase.

Jubilee Gardens

A brief for the park was completed in Spring 2004 and four concept designs unveiled to the public. The successful design was announced in June.

The Waterloo site (Queen Elizabeth Hall, Purcell Room and Hayward Gallery) and Hungerford car park

The SBC and the British Film Institute (bfi) are working collaboratively to decide facilities for the site. Ideas so far have included replacing or modifying the Queen Elizabeth Hall and Purcell Room into performance venues that will complement the RFH.

Hungerford Car Park Arts Development Site

This arts development site is the space between Hungerford Bridge and Jubilee Gardens. Along with the Waterloo site,
it will enable the delivery of the SBC and bfi arts brief.

Hayward Gallery Foyer and Pavilion

The Hayward Gallery reopened in October 2003 following
a £1.8 m foyer extension. Mather has spoken of inserting a glass volume beneath the gallery to counteract the heaviness of the top part.

Recently, South Bank Centre chairman, Lord Hollick, has revisited Terry Farrell’s controversial plans to demolish the gallery which he wants to replace with a five-screen multiplex for the National Film Theatre. Hollick was the man behind the recent bid to up ground rent on the London eye from £65,0000 to £2.5m.