When is Crossrail going to open? Building reveals what we know about the rail project’s delay 

crossrail

With the original opening date of Crossrail come and gone and the project now not guaranteed to open until March 2021 there are still plenty of questions around how the scheme fell so far behind.

As Transport for London (TfL), the Department for Transport (DfT) and Crossrail Ltd race to complete the project, there are plenty of questions around how much it is all going to cost and why the line is not finished yet.

Take a look at what we know so far.

When was the line due to open?

Last year an update by Westminster council let slip online that the central section of Crossrail was scheduled to open on 9 December as part of its follow-up to the decision to reject the pedestrianisation of Oxford Street.

What is to blame for Crossrail’s delay?

When announcing the delay Crossrail said the schedule has been revised “to complete the final infrastructure and extensive testing required”.

Subsequently, the first chief executive of Crossrail Rob Holden blamed a decision to delay procurement of rolling stock for the scheme’s failure to hit its December 2018 opening date. A TfL spokesperson denied this saying: “The procurement of the trains has had no impact on the delayed opening of the central section.”

Mark Wild has blamed the tunnelling for delays at Bond Street and has said the original plan to get the scheme open was “fantasy”.

Were there warning signs?

Nearly two months before the delay to Crossrail was confirmed, the Infrastructure Projects Authority flagged potential issues with the scheme.

In its 2018 Annual Report, the Infrastructure Projects Authority gave Crossrail an amber delivery confidence assessment meaning it was looking at a cost or schedule overrun if “significant issues” were not addressed. It was the first time the project has received a rating below a green category in the six years the report has been produced.

How much is Crossrail going to cost?

At the moment the official known cost is around the £17.8bn-mark. An announcement on 10 December revealed Crossrail was set to cost up to an additional £2bn with the Greater London Authority set to grant TfL a £1.4bn loan to finish off the scheme.

An annual update on Crossrail from then transport minister Jo Johnson in July said the DfT and TfL had agreed to a £15.4bn funding figure. In 2017 that figure was expected to be £14.8bn, meaning costs had increased by £600m.

In October 2018 the project was given a further £350m cash injection, while in November a report from the London Assembly’s budget and performance committee revealed the additional cost that had been agreed so far was only enough to keep Crossrail going until the end of March 2019. This £350m plan has been scrapped in favour of the £1.4bn bailout laid out in December.

The London Assembly’s report also revealed TfL was losing out on up to £190m next year in lost fares and advertising revenue because of the delay.

In January 2019 it is revealed that the scheme only has an 80% chance of being built within its newly approved budget and that it is costing £30m a week.

Eight months later Crossrail chair Tony Meggs admitted the scheme could be another six months late and need a further £400m to finish it off.

When is Crossrail now due to open?

In April 2019 Crosrail boss Mark Wild confirmed the scheme would open some time between October 2020 and March 2021. This does not include Bond Street station.

After the delay was first announched it was meant to open before the end of autumn 2019, but then the London Assembly put a cat among the pigeons suggesting Crossrail may not open until December 2019 – a full 12 months later than it was originally due to open.

report from the assembly’s budget and performance committee said that if TfL, which is helping fund the scheme and will be responsible for running the line, “wants to co-ordinate with the National Rail timetable, it is likely that this means December 2019”.

Key dates in Crossrail’s delay

23 September 2019: Chair Tony Meggs admits Crossrail could be another six months late and need a further £400m to finish it off

30 August 2019: Crossrail’s frustration with the two firms behind Bond Street station breaks into the open with the railway’s board calling for “expected and necessary” leadership changes at the Costain/Skanska joint venture

3 May 2019: A National Audit Office report reveals that the expected cost of finishing seven Crossrail stations has increased by more than £2bn. It also says Crossrail needs to motivate contractors with financial bonuses in order to get the £17.6bn job done in a “timely and efficient manner”.

25 April 2019: Chief executive Mark Wild says the company had earmarked a six month delivery window for the £17.8bn scheme “with a midpoint at the end of 2020” meaning Crossrail will open some time between October that year and March 2021. Bond Street station will not open in that window.

3 April 2019: In a report the Public Accounts Committee says it is “unconvinced” Crossrail’s £2.8bn bailout will be enough, and slams executives for their “unacceptable” inability to explain the delays.

25 January 2019: KPMG’s review of Crossrail’s financial arrangements and governance is publishedIt reveals that there is only an 80% chance that Crossrail will be built within its newly approved budget and that the scheme is costing £30m a week

10 December 2018: It was revealed that Crossrail would cost up to another £2bn to finish  and that no one knew when it would open. Infrastructure and Projects Authority boss Tony Meggs is named chair while former Labour MP Nick Raynsford takes up the vice chair role.

5 December 2018: Sir Terry Morgan officially ousted from his roles at both Crossrail and HS2.

23 November 2018: National Audit Office confirms it will launch a probe into Crossrail’s delay

2 November 2018: TfL and Crossrail announce that Mark Wild will join Crossrail as chief executive, with the company’s current boss Simon Wright stepping down. TfL said Wright’s departure was “as planned”. He was in the job for eight months.

26 October 2018: The government announces it has pumped £350m into Crossrail to keep the project on track.

31 August 2018: It is officially announced that Crossrail’s opening had been delayed by at least nine months to autumn 2019. The company behind the project said the schedule has been revised “to complete the final infrastructure and extensive testing required”.

24 July 2018: An annual update on Crossrail from then transport minister Jo Johnson said the Department for Transport (DfT) and Transport for London (TfL) had agreed to the new £15.4bn funding figure. Last year the figure was expected to be £14.8bn.

6 July 2018: In its 2018 Annual Report, the Infrastructure Projects Authority gave Crossrail an amber delivery confidence assessment meaning it was looking at a cost or schedule overrun if “significant issues” were not addressed. It was the first time the project has received a rating below a green category.