- News

All the latest updates on building safety reformRegulations latest
- Focus

All the latest updates on building safety reform



| Elemental cost summary | |||
| Description | TOTAL £ | £/m2 GIFA | % cost |
| Substructure | 501,758 | 286 | 13.4 |
| Frame | 345,042 | 196 | 9.2 |
| Upper floors, stairs and balustrades | 114,950 | 65 | 3.1 |
| Roof | 101,681 | 58 | 2.7 |
| External walls | 375,637 | 214 | 10.0 |
| Windows and external doors | 15,675 | 9 | 0.4 |
| Internal walls, partitions and doors | 87,780 | 50 | 2.3 |
| Internal finishes | 307,752 | 175 | 8.2 |
| Fittings and furnishings | 149,435 | 85 | 4.0 |
| M&E services | 995,735 | 567 | 26.5 |
| Hard landscaping | 52,250 | 30 | 1.4 |
| Soft landscaping | 56,430 | 32 | 1.5 |
| External fencing, seats, etc | 62,700 | 36 | 1.7 |
| Accommodation block* | 120,175 | 68 | 3.2 |
| Subtotal | 3,287,000 | 1,871 | 87.5 |
| Preliminaries @ 11 % | 350,000 | 199 | 9.3 |
| Main contractor’s overheads and profit @ 4 % | 120,000 | 68 | 3.2 |
| TOTAL | 3,757,000 | 2,138 | 100 |
| NOTE: Gross internal floor area 1757 m2 | |||
| *Accommodation block works out at £1400/m2 based on 85 m2 unit area | |||