This was an application for declaratory relief to establish that the payment claim issued by United Group Infrastructure Pty Ltd dated 14 November 2005 was not a payment claim that is subject to the regime for assessment and adjudication established by the Building and Construction Industry Payments Act 2004.

Pioneer Sugar Mills Pty Ltd alleged that the contract between United and Pioneer was entered into prior to the 1 October 2004, the material date for the operation of the BCIPA.

Pioneer and United had entered into a written contract on the 15 March 2004 for the upgrade of a sugar mill for a renewable electricity generation facility. Subsequently Pioneer and United entered into variation agreement for additional works on 14 October 2004 i.e. two weeks after the material date for the BCIPA.

United contended that the variation was construction work to which the BCIPA applied on the basis that the variation agreement was a construction contract within the meaning of the BCIPA. In addition, United argued that variation agreement evinced an intention on the part of the parties to abandon or rescind the original agreement, substituting in its place, the variation with effect from the agreed variation date i.e. 14 October 2004.