Contractor says it only spent £5.3m of £10m it expected to

Willmott Dixon has managed to claw back nearly £5m of a provision it made for remediation work to a residential scheme it completed in 2012.

In a note accompanying its accounts, which have now been filed at Companies House, the firm said it booked a £10m provision for the work on the unnamed scheme in its 2024 accounts.

But in its 2025 figures, the firm said the cost of work was lower than expected meaning £4.7m of funds have been recovered.

willmott pic

Willmott Dixon said the cost of repair work on the job was less than it thought it would have to spend

It added that the £3.9m it put aside in 2024 to “complete extensive recladding works on a multi-storey residential development completed in 2012” had not increased. It added: “The relevant works were completed in 2025, with no additional exceptional costs incurred.”

The latter job is believed to be a £250m scheme in south-east London called Woolwich Central with the overall repair bill on the job topping £50m.

Turnover last year stayed flat at £1.1bn. Underlying profit edged up £500,000 to £29.1m although pre-tax profit was down to £32m from £47m last time.

But the 2024 pre-tax profit figure had been inflated by a £20m gain for cladding remediation work with part of that figure understood to be related to recoveries it banked following a dispute on Woolwich Central.