facebook
Twitter
Linkedin
Feedback

Saturday04 February 2012

Passivhaus diaries: What the Denby Dale home costs

Passivhaus design Denby Dale
  • Email
  • Comments (7)
  • Save

The Green Building Store reveals the costs behind the Passivhaus home it's building in West Yorkshire

Substructure

Excavation, oversite, reduced levels, foundation trenches and disposal: £3,341.06
Concrete in foundations: £1,192.32
Cavity wall to dpc, 100mm 7KN lightweight block, 300mm polystyrene filled cavity (Dow Floormate 200), 100mm medium dense concrete blockwork/coursed natural stone in lime mortar: £5,618.11
Ground floor slab, compacted hardcore, 225mm extruded polystyrene, radon barrier, 100mm concrete slab power floated with A252 reinforcing: £8,086.14

Superstructure

Cavity walling, 100mm dense concrete block inner leaf, 3 x 100mm mineral wool batts, basalt wall ties, coursed natural stonework in lime mortar, reconstituted reinforced stone lintels: £26,188.06
100mm dense concrete block internal partitioning: £2,944.78
Steelwork to support SW corner of roof and full-height glazed screens: £1,500.00
302mm timber I-beam first floor: £2,847.30
Windows and doors: £22,969.37

Roof structure

Trusses, 500mm mineral wool insulation, wind membrane, battening, concrete interlocking tiles, timber facia, ply soffit and steel galvanised rainwater goods : £9,995.16

Internal joinery work

Chipboard flooring to I-beams, softwood closed staircase and balustrading, OSB board to first floor ceiling, internal doors, linings and skirting: £11,340.86
Stud partitioning with sound insulation: £856.81

Finishes

15mm two-coat wet plaster to all block walls, 12.5mm plasterboard and skim to ceilings and studwork: £8,869.37

Services and fittings

Bathroom and shower room: £8,500.00
Kitchen: £5,000.00
Electrical installation: £6,500.00
Space heating and hot water (natural gas): £3,000.00
MVHR: £4,800.00
Alcohol stove (focal point): £1,000.00
Timber laminate flooring to kitchen and living areas: £2,500.00

External

Drainage: £2,500.00
Site storage: £1,500.00

Total

£141,049.34

Related company resources

Readers' comments (7)

  • How many square metres is the house? And will you be doing any tests to see if the reality matches the theory?

    Unsuitable or offensive? Report this comment

  • The total floor area on 2 floors is 118 m2. We will be monitoring the building with the support of Leeds Metropolitan University, and of course will publish results in due course.

    Unsuitable or offensive? Report this comment

  • Am I right that there is no thermal hot water allowed for in the construction? Seems a lost opportunity Peter

    Unsuitable or offensive? Report this comment

  • Dear Peter, We will at the very least make the house solar thermal hot water 'ready'. We are also looking into a new local authority grant scheme against a charge on the property. We will elaborate later.

    Unsuitable or offensive? Report this comment

  • Hi Bill, Just wondering what the costs are for project development and design work. From my limited experience of PHPP I know its a very thorough and detailed programme, but this means it takes a really long time. So these costs are bound to be higher for the first PassivHaus's that are built but hopefully drop as designers and architects become more experienced in the principles and PHPP. Thanks, Sophie

    Unsuitable or offensive? Report this comment

  • Sophie, I was hoping I was going to get away with no one asking this question! We at Green Building Store/Company have used this project to learn not only how to use Passivhaus Planning Package (the software programme for designing) but about the necessary components and their interaction with the build. We have developed our product range alongside the design process so I find it difficult to separate. However the AECB's Carbonlite PHPP Certification Process manual gives figures gained from the German experience. Using an outside PHPP Consultant with all the help an inexperienced design team would need might be 10000.00 including certification. An experienced design team, they suggest, gets this down to 4000.00 per project. I hope this goes some way to answering your question.

    Unsuitable or offensive? Report this comment

  • Are these costs inclusive or exclusive of VAT?

    Unsuitable or offensive? Report this comment

Have your say

You must sign in to make a comment

sign in register
  • Email
  • Comments (7)
  • Save

Visit the forum

Sign in

Email Newsletters

I'm searching for in
Desktop Site | Mobile Site