Brian Moone

  • Lead times feb2018
    Features

    Lead times: October-December 2017

    2018-02-09T06:30:00

    Our previous look at lead times back in September forecast little alteration, but as it turned out there were no changes at all over the subsequent three months

  • Lead times october2017
    Features

    Lead times: July-September 2017

    2017-10-17T14:29:00

    Companies report being busier, and the lead times of several packages have changed but most have remained level, while little alteration is expected in the next six months

  • Lead times
    Features

    Lead times: July - September 2016

    2016-10-20T06:00:00

    There are capacity issues with some off-site manufacturing but the consensus among other site-based trades is that lead times are stabilising

  • Lead times
    Features

    Lead times: October - December 2016

    2017-02-06T11:41:00

    Lead times have changed for only two packages - the lowest level of change recorded in the last decade. But many packages are reporting difficulty in getting qualified or experienced staff, reports Brian Moone of Mace

  • Lead times index April 2017
    Features

    Lead times: January-March 2017

    2017-04-25T14:00:00

    Lead times have changed for five packages and four are increasing again, but many packages still expect no change in the next six months despite increased workload and enquiries

  • Lead times June 2017
    Features

    Lead times: April-June 2017

    2017-07-18T10:52:00

    Lead times have stayed level, with most packages at the highest level since records began, and little further change is expected over the next six months

  • Lead times: January - March 2015
    Features

    Lead times: January - March 2015

    2015-05-07T06:00:00

    Lead times continue to increase with eight trades on the rise and no reported decreases. Some packages have increased more than once in the last 12 months

  • Lead-times-SMALL
    Features

    Lead times: April - June 2015

    2015-07-20T12:48:00

    With six packages increasing their lead times and widespread reports of increasing enquiries and workload, growth is holding steady. Brian Moone of Mace reports

  • Quality street: Native Land’s Neo Bankside
    Features

    Spotlight: Residential fit-out

    2015-07-20T13:13:00

    As the London residential market continues to boom, the ‘deliverability ceiling’ looms for the supply chain. Brian Moone examines the data

  • Lead-times-SMALL
    Features

    Lead times: July - Sept 2015

    2015-10-19T13:39:00

    Increases to lead times continue, albeit to a smaller number of trades than seen in previous quarters. The major issue forecast going forward is labour shortages

  • Lead times within the specialist brickwork trades have lengthened due to reduced stock levels
    Features

    Spotlight: Managing lead times

    2015-10-19T13:39:00

    With the ripples of recession still being felt through the lead times of many specialist trades, Brian Moone discusses how clients of the supply chain can minimise disruption

  • LTthumb
    Features

    Lead times: Oct - Dec 2015

    2016-02-09T06:00:00

    Increases to lead times continue, and many are forecast to rise in the next six months, as workload and enquiries grow. But staffing is still an issue

  • LTthumb
    Features

    Lead times: Jan - Mar 2016

    2016-04-25T14:37:00

    After a period of increase due to heavier workloads, lead times seem to be levelling off. But fit-out and finishing trades are still in hot demand

  • Lead times
    Features

    Lead times: April - June 2016

    2016-07-21T06:00:00

    Lead times have either remained the same or increased, with burgeoning workloads and enquiries and a shortage of skilled labour making further increases more likely

  • Lead times
    Features

    Lead times July-Sept 2011

    2011-10-21T00:00:00

    Although lead times remain overwhelmingly stable, growth in tower construction in London will affect capacity in steel fabrication, vertical transportation and cladding.

  • Heron tower
    Features

    Spotlight: impact of tower construction

    2011-10-21T00:00:00

    London is a rare area of growth, says Brian Moone, and the projects coming back on line include large and complex towers. Developers and suppliers had better plan early to avoid logjams

  • Features

    Lead times: Oct-Dec 2011

    2012-02-03T00:00:00

    There was very little change in the final quarter, suggesting that the rise in enquiries earlier in the year failed to translate into increased workload. Brian Moone of Mace reports

  • Crossrail
    Features

    Spotlight: Major infrastructure

    2012-02-03T00:00:00

    Vast civil engineering projects such as Crossrail are likely to keep concrete producers busy over the next couple of years, and lengthen lead times for diaphragm wall construction, says Brian Moone

  • Features

    Lead times: January-March 2012

    2012-04-05T00:00:00

    Lead times remain extremely low across all trades, with any bottlenecks being absorbed by the pre-construction programmes of contractors eager to win work. Brian Moone of Mace reports

  • Features

    Spotlight: Impact of archaelogical work

    2012-04-05T00:00:00

    The prospect of finding historic artefacts beneath a site is more likely to strike a developer with fear than excitement. But the real danger arises when it isn’t planned for, says Brian Moone

More by Brian Moone