Structure has been shut since August

A taskforce set up to get Hammersmith bridge up and running again has said it expects to appoint contractors shortly to start repairing pedestals at the structure which has been closed since the summer.

In September, the government tasked the group, chaired by transport minister Baroness Vere, with making sure the 133-year-old cast-iron bridge is reopened.

hammersmith bridge

Source: Shutterstock

The bridge has been closed for more than three months

The taskforce includes project director Dana Skelley, a former head of London’s road network at Transport for London (TfL) and now an independent consultant, along with representatives from Hammersmith and Fulham and Richmond councils as well as the GLA, TfL and the Port of London Authority.

The taskforce has had seven meetings so far and the latest last month said TfL would begin work to repair its two western pedestals as part of wider bridge stabilisation work.

The bridge was closed to motorists in April last year after cracks were detected but remained open to pedestrians and cyclists.

But it was fully closed and fenced off in the middle of August after the cracks were found to have widened during a heatwave.

TfL and local authority Hammersmith and Fulham council are working up a business plan to carry out repair work ahead of it reopening.

In the meantime, a temporary ferry service is planned to start criss-crossing the Thames from next spring.

The news comes as Foster & Partners unveiled plans to build a temporary double-decker crossing within the existing structure of the bridge.

The proposal (see attached), which has been presented to Hammersmith & Fulham council, says pedestrians, cyclists and, potentially, motor vehicles would be able to use the bridge during its repair and restoration.

A new raised truss structure would be built above the existing road deck, featuring a lower level for pedestrians and cyclists and an upper level for cars and buses.

The raised deck would enable existing approach routes for traffic to be used, causing minimum disruption for residents on both banks of the river.

Foster + Partners Hammersmith bridge final

Source: Foster + Partners

The practice has come up with proposals for a temporary bridge

The structure will also provide support for the bridge as well as a safe platform for restoration work to be carried out.

The new truss structure would be assembled in two halves and launched from each side over the existing road surface. It will be supported on each bank and at the two existing piers.

As a result, there will be no added load on the existing bridge deck. Elements of the grade II* listed bridge that need repair, including pedestals, anchors and chains, would be lifted away and transported by barges to an off-site facility for repair and restoration.

Contractors would be able to use the new lower pedestrian deck to access the works. When completed, the temporary raised deck would be removed.

Fosters said that by repairing the bridge off site, the restoration could be done at greater speed and at significantly reduced cost.

The proposal has been put together with bridge engineer Cowi.

Downloads